Quarter Highlights
Alligator Energy Limited (“Alligator”, “AGE” or the “Company”) is pleased to release the 31 March 2024
Quarterly Activities Report.
Uranium - Samphire Project
•
•
Resource extension drilling for the 2024 calendar year commenced 29 January 2024.
•
The Company has provided the SA Department for Energy and Mining (DEM) a formal response to
matters that arose from the public and Govt Departmental consultation on the Retention Lease (RL)
Proposal for the field recovery trial (FRT). The Company anticipates the review period for this response
will be approximately six to eight weeks from lodgement (mid-March).
•
A Program for Environmental Protection and Rehabilitation (PEPR) will be submitted post granting of
the RL. Approval of the PEPR is the final step in the regulatory process to commence on-site
construction of the FRT infrastructure.
•
Fabrication of the containerised FRT plant by Adelaide Control Engineering is essentially complete.
Factory Acceptance Testing of the ion exchange and wellhouse modules is nearing completion.
•
On-site FRT construction and commissioning plans are under development for initiation once both the
RL and supporting PEPR are approved.
•
•
A ground gravity survey was commenced to areas south and north of currently known palaeochannels.
2024 program is focused on drill testing areas outside of the Inferred Mineral Resource envelope. The
drilling at Blackbush is already indicating potential extensions to the current mineralised system. Firstround drilling results and interpretation will be released to the market in the coming days, with a resource
update targeted towards the end of the year.
Further Whyalla community open day sessions were held in February to update stakeholders on our
FRT plans, seek feedback, and engage openly and transparently around all aspects of our project.
Uranium - Big Lake Project
•
A Program for Environmental Protection and Rehabilitation (PEPR) for an initial drilling program was
approved after period end.
•
A preferred drilling contractor for the inaugural drilling campaign at Big Lake has been identified and
contractual arrangements have been finalised.
•
Stakeholder engagement with indigenous group, pastoralists and other tenement holders has been
ongoing, and a maiden drilling program will kick off in 2nd week of May.
Uranium - Nabarlek North Project
•
One uranium intersection reported from 2023 field season (refer ASX release: 19 Dec 23), with minor
anomalous uranium and REE’s in a number of additional holes.
•
2024 field program planned over broader tenement package with combination of airborne geophysics,
ground orientation surveys and up to 8,000 m of focussed RC drilling.
•
Three NT Mines Department co-funding arrangements being developed to seek partial funding for
components of the exploration program (including potential diamond drilling).
•
Field programs to kick off in July after Traditional Owner clearances and acceptance of the Mine
Management Plan (submitted at the beginning of the Quarter).
Energy Minerals - Piedmont Project (Ni Cu Co) and EnviroCopper
•
•
Renewal of the principal Alpe Laghetto licence received from Italian authorities post quarter end.
An information memorandum seeking investment interest from counter-cyclical nickel/copper investors
is in the process of being finalised ahead of planned meetings.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 2 of 25
•
Completion of the Kapunda Project Push/Pull fluid circulation trial by EnviroCopper (AGE: 7.8%
shareholder) demonstrated successful copper leaching and extraction from solution. Drilling approvals
for Alford West Project pending in relation to installation of three hydrogeological testing wells.
Corporate
•
•
Cash balance at quarter end of $32.7M.
•
Alligator’s uranium sales and marketing agency arrangements have been formally transferred from
Traxys North America (Traxys) to Sabasco Ventures LLC, a company controlled by Kevin Smith - the
principal uranium trader for Traxys. Kevin’s consulting role with Alligator under the new arrangement
has been expanded to include investor relations and business development. He will also be continuing
his uranium and energy minerals trading role for Traxys as a consultant.
In January 2024, the Company finalised agreements for the initial investment commitment of $900k in
EnviroCopper Ltd (ECL), an unlisted company undertaking early-stage copper ISR test work and trials
on two oxide copper projects in South Australia. Alligator has the sole funding right to optional future
investments in ECL up to 50.1%.
Plans for the forthcoming quarter:
•
Samphire
- Resource extension drill testing was temporarily halted in the middle of April 2024 for an ~four week
break for lambing season. On return to the field the focus will be on Extension Area 2 and continuing
in Area 1, while also assessing the potential for extensions of the Blackbush mineralisation in the
Blackbush North target area (Figure 2).
- Submission of a Program for Environmental Protection and Rehabilitation (PEPR) for FRT operation.
- Transport of FRT pilot plant and final infrastructure to Whyalla in readiness for on-site construction
post receipt of retention lease and PEPR approvals.
- Initiation of certain optimisation studies (water, power, transport, logistics etc.) required to be
concluded prior to commencement of a feasibility study.
- Scoping in preparation for the feasibility study.
•
Big Lake – A 40-to-45-hole drilling program (circa 5,600m) is planned for commencement in second
week of May 2024. The program is the first step as ‘proof of concept’ for suitable host / concentration
mechanisms for uranium bearing mineralisation in the formations overlying the Cooper Basin.
•
Nabarlek North – Planning for the 2024 field program being finalised including (i) 6,000 – 10,000 line
km of high resolution airborne magnetic and radiometric surveying (ii) RC drilling for up to 8,000 m to
depths up to 300 m and (iii) ground scintillometer and mapping traverses. The field program will be
executed between July and November, subject to Traditional Owner clearances and approval of the
2024 Mine Management Plan (submitted earlier in the Quarter).
•
Piedmont – Renew applications for Sella Bassa, Valmaggia and Gavala licences.
Uranium Market
•
The spot U3O8 price started at $91/lb at the beginning of January, spiked to $107/lb by mid- January
but drifted back to $87/lb by the end of the quarter.
•
•
•
The term U3O8 price increased from $68/lb and rallied up to US$80/lb U3O8 at quarter end.
At start of 2024 there were 60 new nuclear power plants under construction across 16 countries.
The key market drivers during the quarter included: further threat of US sanctions on Russia; US Govt
budget support to domestic nuclear industry; sulphuric acid shortages in Kazakhstan; financial and
trading buyers supporting spot price; a number of long-term U supply contracts being evaluated; fuel
buyers’ running inventories very low; growth in AI data centres located adjacent nuclear power sites.
Refer to additional detail in Market Update.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 3 of 25
Samphire Uranium Project Development
Resource Extension Drilling
AGE through its 2021-2023 drill programs at the Blackbush Deposit and extensive data review of over
1,000 historical drillholes has identified several target areas that remain open and untested. On the back
of 2023’s successful infill drilling at Blackbush, resource extension drilling commenced in late January
2024 to explore several of these target areas outside the existing resource envelope. This comprises
part of a multi-year exploration program outlined in AGE’s Exploration Target Range, which was
announced in December 20231.
The 2024 program will initially focus on:
a)
Drill testing areas immediately adjacent to the limits of the existing Blackbush resource envelope
to continue to upgrade potential project economics - being the open channels indicated with blue
arrows in Figure 1, and
b)
Drill testing new areas in the Blackbush area, in particular Blackbush Extensions 1 & 2 targets
identified in AGE’s Exploration Target Range (see Figure 2 and purple circles marked in Figure
1). These are prospective to host additional uranium mineralisation based on historical drillholes
that have intersected mineralisation, the presence of underlying uranium source rocks and
overlying palaeochannel sediments.
Since late January 2024 to end March 30 holes have been drilled (2,437 metres) with the first-round
program scheduled to continue through to the mid-April when a 4-to-6-week break will be taken to
facilitate pastoral activities.
Figure 1: Updated Inferred resource area outline (blue) and Indicated Resource area outline (red) showing historical
and AGE drillholes focussed within the Inferred Resource envelope. Further resource extension potential shown in
arrows and pink circles.
1 AGE ASX Release 7 December 2023; 02751150.pdf (weblink.com.au)
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 4 of 25
Figure 2: Map highlighting the 11 target area locations within the Samphire Uranium Project Area.
Work undertaken to derive the Exploration Target Range showed that with 64 kms of interpreted
palaeochannel strike length (Figure 2), only 10% of the prospective system (Blackbush Deposit and portion of
Plumbush Prospect) have been well explored, with a further 32% partly drill tested with mineralised
intersections. To date, 58% (over 37 kms) of the prospective areas of the palaeochannel system remain
completely untested, indicating the significant potential for new discoveries in the Project area.
Field Recovery Trial
In August 2023, AGE submitted its full Retention Lease Proposal to DEM to conduct a pilot ISR field trial. A
public review and consultation period for this proposal concluded late September 2023 with formal feedback
received from DEM on 20 December 2023 regarding the public and various SA Government Department’s
submissions.
During the quarter the Company advised that a formal response to the matters raised from the consultation
were submitted to DEM. We have been advised during March 2024 that the review period for this response
will take six to eight weeks pending no further clarifications being required. A Program for Environmental
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 5 of 25
Protection and Rehabilitation (PEPR) is currently being drafted and will be submitted post granting of the RL.
Approval of the PEPR is the final step in the regulatory process to commence on-site construction of the FRT
infrastructure.
Fabrication of the containerised FRT plant by Adelaide Control Engineering is essentially complete with the
ion exchange and wellhouse modules commencing Factory Acceptance Testing on 19 March 2024 prior to
transport to Whyalla. The scope for on-site assembly is being prepared for requests to quote from Whyallabased construction contractors/businesses.
Figure 3: IX columns completed installation inside container. Pump skids in the foreground connected in readiness for
Factory Acceptance Testing.
Acquisition of Ground Gravity
The AGE team has assessed the historical regional geophysics to select the optimal geophysical method for
mapping the Samphire palaeochannel system (host to the uranium mineralisation at the Blackbush deposit
and Plumbush prospect). The Samphire palaeochannel is incised into the Hiltaba Suite Samphire Granite
which provides a lithological density contrast at the contact which ground gravity can successfully detect. The
historical gravity data collected at 100m x 200m grid spacing shows an excellent correlation between gravitymapped paleochannels and drilling (Figure 2).
Daishsat Geodetic Surveyors commenced acquiring ground gravity data south of the Plumbush prospect on
Exploration License (EL) 6350 where historical drilling2 shows the presence of paleochannel-hosted uranium
mineralisation. In addition, Daishsat will acquire gravity data north of the Blackbush system on EL5926 to
delineate further palaeochannels in areas where channels have not yet been delineated but are believed to
exist (Figure 4).
2 Refer UraniumSA ASX Release – 8 April 2011 “Maiden Resource Estimate”,
https://www.asx.com.au/asxpdf/20110408/pdf/41xy4brvxj3d3c.pdf
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 6 of 25
With 64 kms of known palaeochannel strike length so far, the data from the current gravity survey will extend
this and complete Alligators understanding of extensions to the system adding further potential target areas to
its pipeline of future exploration drilling programs.
Figure 4: AGE’s Samphire project tenement holding showing location of historical and recent (AGE) drillholes, historical
ground gravity, the extent of the Samphire palaeochannel system, historical uranium intersections near the Plumbush
prospect1 and location of area acquisition of new ground gravity data.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 7 of 25
Big Lake Uranium (BLU) Project
Highlights for the quarter include:
•
The Program for Environmental Protection and Rehabilitation (PEPR) for the proposed 2024 field
exploration program was resubmitted during the Quarter, following feedback from the DEM. Feedback
included requests for an amended radiation management plan and the recommendation to have a
Class 2 water driller on site to manage any potential confined aquifer intercept (the PEPR was approved
at the time of this report’s writing, April 2024).
Drilling tender released to the market during the Quarter and revised following the above
recommendation from the SA DEM. Only two suitable tenders were received and were assessed for
value and safety (tender awarded at the time of writing this Quarterly report).
Final planning for the maiden drilling program has been completed. The program remains unchanged
from earlier proposals with 5,600 m of air-core drilling planned over 40 – 45 holes, with average depths
of 140m. Holes will be assayed to further assist with fine-tuning the seismic interpretation and data
integration (see Figure 5).
Program planning is working on a start date for drilling of early to mid-May and completion by the end
of June.
•
•
•
Figure 5: Big Lake Project. AGE Big Lake drilling proposals for March/April 2024 as a series of fences. Sites were
inspected and cleared by traditional owners in November 2023.
Alligator Rivers Uranium Province (ARUP)
•
All geochemical assays for the 2023 Nabarlek North field program have been received by the end of
Quarter. Alligator previously reported a uranium intersection in one hole of 3 m @ 0.12% U3O8 which
is an extension of the U40 prospect (see ASX release of 19 December 2023 https://wcsecure.weblink.com.au/pdf/AGE/02755611.pdf).
•
Based on a preliminary review, minor anomalous uranium was found in a number of other holes. The
Company continues to review critical minerals potential in the region, and there were a number of
anomalous REE values found in areas of clays in contiguous holes. While results were deemed below
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 8 of 25
economic potential, Alligator will maintain an assay focus on REE’s particularly as we move into more
granite / ionic clay type areas.
•
A Mine Management Plan was submitted in February to cover the 2024 Nabarlek North exploration
program. The program proposals include a high resolution airborne magnetic and radiometric survey
of 100 m line spacing to cover the entire project area, ground reconnaissance work (field mapping,
scintillometer traverses and geochemical sampling), along with approximately 10 to 15 sites of
targeted Reverse Circulation (RC) drilling to depths of 300 m (see Figure 6).
•
In contrast to the previous two field seasons, the 2024 program will prioritize features across the entire
(granted) project area – subject to consultation and clearance with Traditional Owners.
Figure 6. Nabarlek North – 2024 target portfolio, pending new airborne geophysical surveying (June) and ground
reconnaissance work. It is anticipated that 10 -15 focussed sites for fences of RC drill holes will be generated, for
drilling in August – October, 2024. Note Target U40N represents an along-strike extension of DevEx’s U40 Prospect
into Alligator Energy’s Nabarlek North Project Area (green polygons)
Piedmont Nickel Cobalt Project - NW Italy
•
Post quarter end, Alligator was advised by the Mines Department of Regione Piemonte that the
principal Piedmont licence, Alpe Laghetto, has been renewed and is now held in the name of Alligator’s
Italian subsidiary.
•
In agreement with Alligator’s joint venture partner, market interest will be assessed from a countercyclical Ni Co resource investor to progress the next stage of exploration for the Project. An information
memorandum is nearing completion and takes into account the Laghetto license along with the
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 9 of 25
applications covering Sella Bassa, Gavala and Valmaggia. The three former license areas have seen
limited work outside of ground truthing of mineral occurrences but variably contain economic grades
of Cu-Co-Ni and Au in some cases.
•
The three license applications are being submitted with exploration recommendations (similar to those
proposed for Laghetto), to better gauge regional prospectivity of the fertile mafic sequences.
Figure 7. Piedmont project area. Laghetto tenure under renewal, Sella Bassa, Gavala and Valmaggia require
lodgement of new applications.
Investment in EnviroCopper Limited
•
Successful completion of a Push/Pull fluid circulation trial at Kapunda Project showing copper
extraction from solution, in line with CSIRO’s large particle column leach testing done under the CRCP Research Grant in 2021.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 10 of 25
•
Next stage for Site Environment Lixiviant Trial (SELT) activity at Kapunda is well under way, with
drilling of 5 spot pattern of injection/extraction wells and monitor bores nearing completion. Suitable
copper grades were intersected in injection and extraction wells. Construction phase for lixiviant
circulation to occur once approvals received, expected Q2 2024.
•
Drilling approvals for Alford West Project pending for undertaking 3 wells for hydro testing (planned
Q2 2024).
Market Update
•
The spot U3O8 price started at $91/lb at the beginning of January, spiked to $107/lb by mid-January
but drifted back to $87/lb by the end of the quarter.
•
The term U3O8 price started the quarter at $68/lb and rallied up to US$80/lb U3O8 and when used in
contracts is typically escalated annually from the starting point.
•
At the start of 2024 there were 60 new nuclear power plants under construction around the world,
across 16 countries.
The key market drivers during the quarter were:
•
Threat of US sanctions on Russian origin nuclear fuel, which provides over 30% of US nuclear fuel
needs, with no viable alternative supply. Russian nuclear fuel is still the only natural resource from
Russia not to be sanctioned due to the Ukraine situation.
•
The US Government passed a new budget in the quarter that earmarks US$2.7 billion dollars to the
development of a domestic US nuclear fuel cycle and provides further long-term financial support for
the nuclear industry in the US.
•
Reports of serious sulphuric acid shortages in Kazakhstan, which produces over 40% of the worlds
U3O8 supply, that will potentially limit the growth in production from the largest uranium producer in
the world. It’s estimated to take up to four years to design, build and commission a new sulphuric acid
plant which limits the ability for Kazak production increase.
•
The Sprott uranium fund (SPUT) only bought 3.8M lbs of U3O8 during 2023 (versus 10M+ in 2022)
but the price rallied up 89% during the year with competitive speculative buying.
•
Utilities came back to the market and investors are competing with primary users for available spot
uranium, with no large secondary inventories around and most large producers nearly sold out for the
next four years.
•
Fuel buyers are running inventories down very low to delay / avoid having to come to market while
price is high and supply is tightening. However there are still uncovered requirements that will require
them to come back to market, with limited uncommitted inventory and an increasingly tight
supply/demand balance.
•
The growth in AI data centres is increasing the demand for electricity, while trying to strike an ESG
and low carbon footprint. This has been met by exclusive deals and nearby locations adjacent nuclear
power plants. This is a growing trend and new demand for nuclear power, SMR’s and ultimately
uranium.
•
Small Modular Reactor (SMR) vendors are increasingly winning MoU’s and orders for new plants
around the world and have started coming to market to secure fuel for these. This is new demand,
from a new generation of nuclear plants that are forecast to add significant growth in annual uranium
requirements as the decade progresses.
•
Large, multinational investment firms, predominantly from the US, are increasingly investing in
uranium and nuclear power as part of the energy transition and drive to net zero carbon emissions.
The stigma of investing in the sector is largely gone.
•
Despite rising uranium prices, the supply response has been very slow. After established producers
announced plans to return to nameplate capacity, and re-start mines bring on idled sites, there is
minimal new production, with no substantial new production coming online for the next several years.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 11 of 25
•
Due to the low impact uranium prices have on the cost of electricity from nuclear power generation,
there is largely inelastic demand that will have no near-term demand destruction despite rising prices.
•
Energy transition investors and large technology companies are increasingly turning to nuclear
technology investments and increasingly making investment in SMR plant vendors, to accelerate the
roll out of these new nuclear plants. This should further support and increase the long-term
fundamentals of nuclear power.
Other significant nuclear industry news included:
•
The French Energy Ministry tabled a draft submission during the quarter for eight more reactors (14
new reactors in total). The French government announced plans to expand the country's nuclear fleet,
with a new draft law calling for the construction of 13 GWe (~8 new EPR2s), beyond the already
planned six units. The proposed program will be debated in parliament and discussions with
lawmakers may explore beyond the initial goal of 14 EPR2s, emphasising the country’s need for
significant growth in renewable energy capacity.
•
The EU has labelled nuclear as “strategic” for its decarbonization goals. Nuclear is now classified as
a strategic technology in the Net-Zero Industry Act. This is an important step as it provides the benefit
of a streamlined permitting process.
•
In early April 2024, the Chairman of India’s Atomic Energy Commission stated aims to increase the
country’s nuclear capacity from ~8 GWe to ~100 GWe by 2047. India’s Prime Minister had previously
announced a plan to add a total of 18 reactors with a cumulative capacity of 13.8 GWe by 2031-2032,
aiming to boost the country's share of nuclear energy to 22.5 GWe. During the planned shift away
from coal power, India will then become the second largest planned reactor build-out after China.
Corporate
In mid-December 2023, Alligator announced that it planned to expand its energy minerals interest by making
a strategic investment in EnviroCopper Ltd (‘ECL’) with future optionality to further invest to acquire up to
50.1% of the company. Alligator and ECL entered into a Subscription Agreement for the initial transaction, and
on completion of the transaction agreed to enter into a Shareholders’ Agreement governing Alligator’s further
staged investment options in ECL.
The conditions precedent to completion of the Subscription Agreement were met on 24 January 2024 and
Alligator made an initial investment of ~$0.9M for a 7.8% interest in ECL.
The Agency Agreement with Traxys North America Inc (Traxys) agreed in May 2021 was terminated effective
31 December 2023 and a new consulting agreement has been put in place with Sabasco Ventures LLC, a
company controlled by Kevin Smith, who remains the principal uranium trader at Traxys on a consulting basis.
The terms of the agency and consulting agreement with Alligator envisage the provision of similar services
(ASX announcement: 10 May 2021) with the exception (due to balance sheet backing) of inventory financing
and structured financing solutions in the lead-up to a development decision. Kevin will however assist with
North American investor marketing opportunities either with the CEO or as agreed, and input into business
development opportunites. The agreement includes the following key commercial terms and conditions:
•
•
•
•
worldwide exclusivity during the term of the Agreement for the marketing of U3O8 produced, owned
or controlled by Alligator or any of its affiliates with the exception of any project financing related
arrangement.
initial fixed term of two years from the date of execution of the Agreement and then annual renewal
with a 90-day notice period for termination.
Sabasco and Alligator to confer, discuss, finalise and maintain a marketing and sales plan for U308.
the duties and function of Sabasco include pre-contracting, contracting and contract management
associated with production and delivery and business development.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 12 of 25
•
•
•
an initial upfront compensation covering the first two-year period of US$250,000 in fully paid ordinary
shares in Alligator (AGE Shares) at an issue price based on the 20-business day VWAP share price
prior to execution of the Agreement and an annual fee of US$125,000 thereafter to be settled in AGE
Shares or cash.
uranium contracting commission payable at market rates on a staged basis for sales secured under
long-term contracts on a tiered annual production basis. The commission to be based in US dollars
and calculated on the notional value of the underlying contract; and
termination rights in certain circumstances.
Capital Structure and Listing Rule 5 disclosures
At 31 March 2024, the Company had the following capital structure and cash balances:
As at 31 March 2024
Cash Balance
A$32.7M
Ordinary Fully Paid Ordinary Shares (AGE)
3,862.3M
Listed Options 7.8c (Exp 28/11/25) (AGEOC)
273.9M
Unlisted Options 8.1c (Exp 01/12/25)
132.0M
Unlisted Employee Incentive Performance Options
28.9M
Big Lake Performance Shares (Exp 10/12/24) (see Appendix 1)
30.0M
Expenditure on exploration and evaluation activities during the March 2024 quarter totalled $1,497k (previous
quarter - $3,106k) and related principally to advancing the Samphire Project and preparing for the inaugural
drilling program at Big Lake.
Payments to related parties including non-executive director fees and the salary of the CEO and Managing
Director for the March quarter totalled $130k (previous quarter $130k).
This announcement has been authorised for release by the Board.
Contacts:
For more information, please contact:
Mr. Greg Hall
Mr. Mike Meintjes
CEO & Director
CFO & Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 13 of 25
Competent Person’s Statement
Uranium
The information in this announcement that relates drillhole data, QAQC and geology aspects related to the project is based
on and fairly represents information provided by Dr Andrea Marsland-Smith who is a Member of the AusIMM. Dr MarslandSmith is employed on a full-time basis with Alligator Energy as Chief Operating Officer, and has sufficient experience which
is relevant to the style of mineralisation and type of deposit under consideration (including 21 years in ISR uranium mining
operations and technical work) and to the activity she is undertaking to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr
Marsland-Smith consents to the inclusion in this release of the matters based on her information in the form and context
in which it appears.
The information in this announcement
Share your feedback
Discover