Annual Report - 2025
Released
Released
Announcement PDF
a
2024 -2025
Annual Report
ACN 140 575 604
Alligator Energy 2025 Annual Report 2
Contents
Alligator Energy is a responsible and progressive
uranium and energy metals explorer and emerging
producer
Our aim is to discover, source and economically
extract these needed commodities with an
innovative approach, with either zero or minimal
impact, and with positive value and experience for
our stakeholders and communities.
03 Strategy and highlights
14 Chairman and CEO's message
17 Uranium market summary and
outlook
21 Project locations
23 Environment, social and governance
36 Tenement register
39 2025 Financial report
124 Competent person’s statement
127 Mineral resource statement
133 ASX Information and Corporate
Directory
Alligator Energy 2025 Annual Report 3
Strategy and
Highlights
Alligator Energy 2025 Annual Report 4
Alligator Energy’s
Strategy
Our strategy is focused
and straightforward:
Advance the Samphire Uranium Project
through field recovery trial, resource
growth, feasibility study, stakeholder
engagement, initial offtake contracts,
Mining Lease approvals, financing, and
in-situ recovery (ISR) production.
Expand the Big Lake Uranium Project
discovery and further identify and
evaluate targets in the highly prospective
Alligator Rivers Project.
Acquire or JV additional uranium or
energy mineral assets in key target
geographic regions.
Collaborate on the application of in-situ
recovery as a mining technology and
focus on adding value to our investment
holding in EnviroCopper.
Continue to develop our nuclear utility
customer relationships to enable future
establishment of long-term offtake
contracts at supportive pricing and
economics for our Samphire Uranium
Project.
Broaden our investor relations
internationally.
Alligator Energy 2025 Annual Report 5
Highlights 2024-2025
Samphire Project, South Australia
Alligator Energy 2025 Annual Report 6
Continued Resource Definition and Extension Drilling at the Blackbush
Deposit
Drilling activities continued during the first half of the financial year at the Blackbush Deposit.
Key achievements from these activities included:
Uranium mineralisation was extended by a cumulative 500m of strike length outside the
known Blackbush West (December 2023) Mineral Resource Envelope.
Significant uranium intersections encountered in roll fronts focused on the western and
southern areas of Blackbush West.
A total of 61 holes were drilled for 5,158m with alignment noted to the strategy outlined in
Alligator’s Exploration Target Range released in December 2023.
A continued refinement in the understanding of the Blackbush West uranium roll fronts
delivered further targets outside of the December 2023 Inferred Mineral Resource
Envelope.
Further confidence in the Mineral Resource Estimate at the Blackbush
Deposit
An update of the JORC Mineral Resource Estimate (MRE) for the Blackbush deposit
was completed late in the financial year with the following key outcomes:
With the addition of the 2024 resource drilling, the Indicated portion of the MRE was
further increased by 10% (1.3Mlbs) from the previous MRE to 14.2 Mlbs at an average
grade of 786ppm U3O8. The increase in the indicated portion and average grade reflects
an increased accuracy and integrity of the Blackbush mineral resource model ready for
well-field design.
The Total MRE (Inferred and Indicated) increased by 3% (0.5Mlbs) to 18.0 Mlbs
(14.2Mlbs Indicated and 3.8Mlbs Inferred) at an average grade of 676ppm U3O8.
Alligator Energy 2025 Annual Report 7
Field Recovery Trial preparation work positions the Company well for the
construction and operations phases
In late December 2024, the Group received the draft Retention Lease (RL) tenement documents
from the SA Department for Energy and Mining (DEM) including the proposed Conditions of
Operation with which the Group must comply while operating the Field Recovery Trial (FRT). On
accepting the conditions attached to the RL, the Group received confirmation from the DEM of the
grant of a RL for the conduct of the FRT, on 13 January 2025.
The RL Conditions were factored into the Program for Environment Protection and Rehabilitation
(PEPR) which was approved by the DEM and co-regulators post year end. The PEPR approval
provided the ’green light’ to commence on-ground construction activities associated with the FRT
ahead of operating the trial which will be through the first quarter of 2026. Fabrication of the FRT
pilot plant was completed by Adelaide Control Engineering (ACE) in 2024 and the seven
containerised plant modules including the reverse osmosis plant transported to Alligator’s Whyalla
yard ahead of the approval to commence construction works on site.
Whyalla-based contractor, Ahrens Group Pty Ltd, was selected for the on-site construction of the
FRT pilot plant and associated civils, along with procurement of on-site lab, ablutions/office
buildings, pipe works and pumps to connect with the trial-production-well patterns. Their team and
sub-contractors from the Whyalla region were mobilised by early October and initial civil works
commenced, with up to an estimated 25 skilled construction and trades people required for the
circa 3-month construction and commissioning phase.
Alligator Energy 2025 Annual Report 8
Field Recovery Trial to provide a higher level of confidence in the
assumptions applied in the December 2023 Scoping Study –
Definitive Feasibility Study to follow
The objectives of the FRT are to confirm key parameters of a future production operation and
marks an important step toward development. Parameters to be assessed include uranium
recovery from the well patterns, in-situ chemistry, hydrogeology, reagent usage, ion exchange
efficiency and other environmental and economic factors.
Data and learnings further de-risk the Project and provide the necessary inputs to a definitive
feasibility study and Mining Lease Application to be commenced during 2H 2026.
Recap of the highlights from the updated December 2023 Scoping Study:
69% increase to the post-tax NPV8 to A$257M.
Reduction in payback period by 30% to 2.45 years.
Net project cashflow (post Capex and tax) increase of 52% to A$467M.
20% step-up in the steady state annual Production with only a minor 2% increase in
capital expenditure forecast to A$131M.
Favourable average All In Sustaining Cost (AISC) of A$47.58/lb U3O8 (US$33.31/lb
U3O8) with range of A$45.20/lb to A$49.96/lb.
Alligator Energy 2025 Annual Report 9
Big Lake Uranium Project –
Cooper Basin, South Australia
Alligator Energy 2025 Annual Report 10
A significant new uranium discovery declared at the Big Lake Project
An inaugural drilling program commenced late in the 2024 financial year with the objective of
calibrating the seismic/AEM interpretations with the potential for identifying amenable sedimentary
host rocks for the existence of uranium roll-front systems within 400m of surface.
Drilling at Site 10 on EL6367 early in the drilling campaign returned very encouraging indicators of
sands within the Tertiary Namba Formation at depths up to 110m and elevated uranium levels well
above background values. Follow up in August 2024 with a further four holes intersecting
significant thicknesses of anomalous uranium mineralisation with a significant new uranium
discovery declared in August 2024.
The discovery is the first proof of concept that significant uranium is present within the Lake Eyre
basin sediments that lie above the hydrocarbon-rich Cooper Basin and within potentially In-Situ
Recovery (ISR) amenable host and depths.
Laboratory chemical assay results included:
AC24-021 20 m @ 110 ppm U from 106 m
AC24-022 35 m @ 117 ppm U from 93 m
AC24-023 5 m @ 47 ppm U from 104 m
AC24-025 10 m @ 138 ppm U from 108 m
A follow-up drilling program commenced in late February 2025 but had to be delayed after only
three drill holes due to floodwaters from Western Queensland inundating the Project area.
At the date of this report, access to the Project area to allow drilling activities to recommence is still
not possible.
A prospectivity review for the entire Cooper Basin is ongoing, including analysis of all available drill
hole databases for potential indicators of uranium source, migration and deposition.
Alligator Energy 2025 Annual Report 11
Alligator Rivers Uranium Projects –
Tin Camp Creek (TCC), Beatrice and
Nabarlek North, Northern Territory, Australia
Alligator Energy 2025 Annual Report 12
2024/25 Field Program results
A new uranium mineral occurrence (Bully Prospect) was identified through drilling during the 2024
exploration program at Nabarlek North. This was encountered along an interpreted structure
approximately 4km to the northeast of the U40 extension. Here, 1m @ 108ppm U3O8 in NNRC24-
019 from 83m was intersected with additional low-grade anomalism at other intervals and in a
neighbouring hole associated with vector chlorite/sericite alteration in the target Cahill Formation.
Rare Earth Elements were also investigated at the TCC Project during the 2024 exploration
program with peak results highlighting 3.16% Total Rare Earth Oxides (TREO) in grab samples of
which 0.68% is comprised of Magnet Rare Earth Element Oxides (MREO).
Opportunistic grab samples during reconnaissance at the TCC Project highlighted the potential for
high purity silica (HPS) to occur in the region through massive quartz veining. Two samples were
collected over 8km apart in separate vein systems returning up to 97.84% SiO2 through whole rock
XRF analysis by Bureau Veritas Minerals.
HPS is used in specialist technologies and chips for AI and solar cells in the renewable sector.
While 98% purity SiO2 is preferred in industry, improved sampling procedures and handling could
potentially improve results and understanding of the potential.
Co-Funding grants towards the 2024 exploration program was received from NT Government. The
grants contributed to the funding of the 2024 airborne geophysics and greenfields exploration RC
drilling at Nabarlek North. Combined co-funding support totalled approximately $180k.
Alligator Energy 2025 Annual Report 13
Corporate
Significant institutional, sophisticated investor support for the recent capital
raise
In June 2025, the Group received firm commitments to raise $17.25M (before costs) via placement
to institutional and sophisticated investors. The Placement was strongly supported by institutional
investors, both in Australia and overseas and has materially strengthened the Alligator share
register. The Placement involved the issue of 556M new ordinary shares at $0.031 per share and a
one for two option issue (Options) at an exercise price of $0.047 with a two-year life from the date
of issue.
The terms of the Placement required the Group to seek Shareholder approval prior to issue of the
Options and then to seek quotation, subject to compliance with the relevant ASX Listing Rules and
the Corporations Act. Shareholder approval was obtained at a general meeting of the Company
held on 28 August 2025.
The funds raised through the Placement enables the Group to accelerate progress and expand its
work programs on its key uranium projects and enable evaluation of other business development
opportunities.
Strategic investment in EnviroCopper Limited (ECL) progresses
Collaboration on the application of the in-situ recovery technique for mineral recovery continued
during the year.
The Group also completed a further subscription for fully paid ordinary shares in ECL for $871k
and now holds a 15.61% interest in ECL. Alligator’s sole funding rights have, however, lapsed and
ECL undertook ongoing investment discussions with international investors focused on copper ISR
for a significant equity injection. In October 2025, a cash contribution of $3.5m was secured from
an international company with the option to convert to equity in ECL within a five year period.
In the last quarter of the financial year, ECL received approval from the Department for Energy and
Mining, for a 90 day in-ground Site Environmental Lixiviant Trial (SELT) to confirm economic
modelling for potential copper extraction. The SELT pre-conditioning is underway, and the trial is
expected to run through into the new year. If successful, this trial may lead to feasibility studies and
a mining lease application under the Mining Act (SA) for a Copper ISR mine at Kapunda.
Executive leadership changes
Effective 1 July 2025, Greg Hall, the CEO and Managing Director, moved to a part-time role of
Executive Director - Marketing & Investor Relations and Andrea Marsland-Smith, the incumbent
COO, assumed the CEO role.
Alligator Energy 2025 Annual Report 14
Chairman and
CEO’s message
Alligator Energy 2025 Annual Report 15
The Alligator Board would like to express its gratitude for the ongoing
support it has received from its investors, stakeholders, and growing team
through the 2025 Financial Year.
This year, following the tireless efforts of our team through an extended approvals process, we
were pleased to receive the final approval post year-end to commence construction of the
Samphire Field Recovery Trial. Construction is now in full swing.
The Board was also thrilled to finish the year with the announcement of Andrea Marsland-Smith’s
appointment as CEO, following her successful tenure as Chief Operating Officer. Andrea has vast
experience in uranium exploration and operations, and in particular in-situ approvals, development
and operations. Greg Hall has been CEO since 2018, taking Alligator from a small Arnhem land
explorer to advancing the next Australian ISR uranium project. We are pleased that Greg remains
with the Company as Executive Director.
The Company also finished the year in a good financial position, with a robust cash balance of
$30.1 million following the June 2025 share placement of $17.25 million before costs that was
strongly supported by institutional investors, both in Australia and overseas. This support has
materially strengthened the Alligator share register.
Looking at our projects, Samphire Uranium Project’s Blackbush drilling program successfully
expanded and improved our confidence in the uranium resource, with medium to high-grade
intersections discovered within and beyond existing resource boundaries. The updated JORC
Mineral Resource Estimate was consequently increased to 18.0 million pounds at an average
grade of 676ppm U3O8.
As well as resource drilling, three investigation wells were successfully drilled towards the end of
the period, to establish the groundwater baseline for the Field Recovery Trial.
In anticipation of the recently received approvals and permits, fabrication of the Field Recovery
Trial pilot plant was completed in Adelaide at the start of the period, with equipment transported
and stored in Whyalla. The Company selected Ahrens Group Pty Ltd as the preferred Whyalla-
based contractor for on-site construction activities, including civil works and pipework installation
with mobilisation plans underway at the time of writing.
Alligator received a Retention Lease for conducting the field recovery trial in January, marking a
crucial milestone for assessing the economic development of the Blackbush deposit at Samphire.
The Program for Environment Protection and Rehabilitation approval, comprising the operating
procedures for the trial along with the operating permits, was approved post year-end, representing
the final regulatory steps.
Looking to our other projects, the Company acquired the Big Lake project in 2019 and conducted
the inaugural drilling at Big Lake this financial year. The 27 hole program, totalling 3,413m,
confirmed that significant uranium is present within the Lake Eyre basin in sediments that lie above
the hydrocarbon rich Cooper Basin – with economic grades in sand units of 5-20m thickness within
110m of surface. Alligator received approval for follow-up drilling, however flooding in the Cooper
Basin Cooper Basin during April 2025 postponed activities with a revised drilling program being
prepared for early in 2026. We were honoured to be recently awarded the ‘Discovery of the Year’
at the 2025 Australian Mining Prospects Awards. Congratulations to the Alligator team!
Alligator Energy 2025 Annual Report 16
Drilling at Nabarlek North completed 22 holes for 3,526m, discovering new mineralisation at the
Bully prospect (~4km east of U40), and surface sampling identified multiple uranium anomalies
including 4,120ppm at historic Gorrunghar Prospect. Notable critical minerals results at the Tin
Camp Creek Project included 3.16% Total Rare Earth Elements.
Towards the end of the period, EnviroCopper Limited, in which AGE has a 15.61% interest,
received DEM approval for a 90-day trial to confirm copper extraction economics. This approval
process created DEM's template for other ISR projects, potentially accelerating future project
timeframes. Pleasingly, the first stage pump testing at the Alford West project established
favourable hydrogeological parameters for ISR operations.
Long-term U3O8 pricing remained stable at US$80/lb throughout the year. In contrast, spot prices
experienced notable volatility over the same timeframe, declining from $85/lb to $78.5/lb and
reached lows of $63/lb in the March quarter before recovering.
The strengthened uranium market was primarily driven by the US announcing four executive
orders designed to restore America's nuclear energy leadership. This followed a US Department of
Energy report showing that AI growth had turbocharged data centre power consumption which
could triple again by 2028.
Another significant market development over the year was major technology companies such as
Meta, Microsoft, Amazon, and Google securing nuclear power arrangements, exemplified by
Meta's 20-year power purchase deal with Constellation Energy. These deals provide significant
private sector validation for nuclear power and add to future demand.
China’s continued commitment to nuclear power, with 30 reactors under construction and the
recent approval for 10 new reactors, is also a strong growth theme which is projected to increase
China's nuclear capacity from 60 GW to 200 GW by 2040.
South Australia's established uranium regulatory framework provides a stable and lower
jurisdictional risk for US and European utilities seeking to secure uranium offtake arrangements.
Alligator experienced considerable interest, contingent on successful trials and approvals, in
potential uranium supply from Samphire, during a series of meetings with prospective nuclear utility
customers over the year.
We look forward to the year ahead with the
expanded leadership team, a strong balance
sheet, and strong momentum at the project
level.
On behalf of the Board, we thank all
Traditional Owners, communities, and
pastoralists whose lands we have operated
upon, all stakeholders for their loyalty and
support, and the extended and growing
Alligator team for the excellent work and
ongoing commitment.
Paul Dickson
Chairman
14 October 2025
Andrea Marsland-Smith
Chief Executive Officer
14 October 2025
Alligator Energy 2025 Annual Report 17
Market Summary
and Outlook
Alligator Energy 2025 Annual Report 18
Uranium market summary and outlook
The uranium market since the beginning of 2025 has demonstrated remarkable resilience and
transformation. While Q1-Q2 spot price weakness tested investor conviction, the fundamental
drivers of supply constraint and demand growth remain firmly intact. The second half of 2025 to
date has seen price recovery and renewed recognition that structural deficits persist.
Looking toward calendar year 2026, the convergence of multiple factors—Kazakhstan production
discipline, Canadian production challenges, technology sector nuclear commitments, reactor life
extensions, and diminishing secondary supplies—points toward a tightening market that are likely
to support prices in the $US90-100+ range.
For Alligator Energy and the broader uranium development sector, this represents an exceptional
environment to advance projects toward production, with strong fundamentals supporting both
project economics and strategic value.
The emergence of technology companies as nuclear power buyers adds a new dimension to the
market that reduces dependence on traditional utility procurement cycles and creates additional
pathways for project development and financing.
The uranium market's transformation from oversupplied commodity to strategic resource is well
underway, with 2026 positioned to be a pivotal year as supply tightness intensifies and new
demand sources materialize into actual uranium purchases.
Market Fundamentals (2025-2026)
Supply Constraints are Real and Persistent: Production cuts from Kazakhstan and
Canadian operations plus restart project commissioning delays demonstrate supply
response is slower than demand growth, supporting structural deficit thesis
Demand Transformation is Underway: Technology sector nuclear commitments
represent paradigm shift beyond traditional utility demand, creating a new floor under
uranium requirements
Price Recovery Trajectory Intact: Despite Q1-Q2 weakness to $US63.50, the recent
recovery to $US82-84 range demonstrates underlying support, with $US90-100 targets
reasonable for 2026
Term Market Signals True Value: Continued strong term contracting at $US85-90+ per
pound reflects where informed buyers see long-term price equilibrium
Volatility Creates Opportunity: Spot market swings create development and acquisition
opportunities for well-capitalised, strategic companies
Alligator Energy 2025 Annual Report 19
Demand Revolution: The AI – Nuclear Nexus
Big Tech's Nuclear Pivot Accelerates
Data centre power demand could triple by 2030 due to the massive processing power
requirements of generative AI, according to Boston Consulting Group projections. This isn't
speculative future demand—data centres are being built now, creating near-term power capacity
constraints that are driving urgent nuclear development timelines. This represents not just
incremental demand growth but a paradigm shift in who the uranium industry's customers are.
Unlike traditional utility demand that grows incrementally and predictably, technology sector
demand is expected to occur in large bites, be more urgent, and with a willingness to pay premium
prices for reliable baseload power. This occurrence will create a new "floor" under uranium
demand that wasn't present in previous market cycles.
Over recent months, Amazon, Google, and Microsoft have all announced ambitious deals to
acquire nuclear energy for their operations, with some plans aiming to secure energy in the near
term from existing power plants while others focus on long-term investments. These are multi-
billion-dollar commitments that signal nuclear power as central to Big Tech's infrastructure
strategy:
Microsoft: Beyond its previously announced TerraPower partnership, Microsoft has
expanded its nuclear footprint through power purchase agreements and direct
investments. Microsoft and OpenAI have discussed building a linked network of data
centres that would constitute a massive supercomputer dubbed Stargate.
Amazon Web Services: AWS VP of global data centres Kevin Miller stated "AI is driving
a significant increase in the amount of data centres and power that are required on the
grid. We view advanced new nuclear capacity as essential". Amazon has now made
concrete investments in multiple small modular reactor (SMR) developers and power
purchase agreements.
Google & Meta: Both companies have announced partnerships with nuclear developers
and are actively pursuing offtake agreements to secure dedicated nuclear capacity for
their data centre networks.
Alligator Energy 2025 Annual Report 20
Market Structure and Supply- Demand balance
One of the most important dynamics in the current uranium market is the persistent
divergence between spot and term market behaviour:
Term Market Strength: Utilities and now technology companies continue to prioritise long-term
supply security over price optimisation. Multi-year contracts are being signed at prices significantly
above current spot levels, reflecting buyers' assessment that near-term spot weakness doesn't
represent long-term market reality. This term market strength provides cash flow visibility for
producers and supports initial investment in new production capacity.
Spot Market Volatility: The spot market remains thin and volatile, subject to trading by financial
participants and discretionary buying by utilities. The 18-month low of $63.50 in March 2025
followed by recovery to ~$84 by October demonstrates this volatility. However, spot market
weakness increasingly appears to be buying opportunities rather than signals of fundamental
oversupply. Despite spot price volatility, the fundamental long-term supply-demand balance
remains in deficit.
Demand Side factors:
Traditional nuclear fleet: stable and growing as reactors extend operations and new
builds progress
Policy changes supporting nuclear: particularly in European countries and US
New reactor construction: particularly in China, India, and emerging markets
Reactor restarts: previously shuttered facilities being reactivated (e.g., Three Mile Island)
Technology sector: new demand category with significant growth potential
Existing reactor up-rates: increasing output from current fleet
Supply Side factors:
Primary production growth: slower than projected due to operational challenges
Kazakhstan constraints: sulphuric acid supply, labour, regulatory issues
Canadian challenges: ramp up delays at Cameco and others
African production: Namibia stable but not growing significantly – likely needs higher
market pricing
Secondary supply: diminishing inventories from decommissioned weapons and utility
stockpiles
The maths continues to point toward structural deficits that must be filled either through significant
price increases that incentivise additional new production or through demand-side destruction
however nuclear power's role in decarbonisation makes demand-side destruction unlikely.
Alligator Energy 2025 Annual Report 21
Project
locations
Alligator Energy 2025 Annual Report 22
Project Locations
Alligator Energy 2025 Annual Report 23
Environment,
Social and
Governance
Alligator Energy 2025 Annual Report 24
Environment, Social and Governance (ESG) -
Our Philosophy
Alligator Energy aims to incorporate Environmental Social and Governance (ESG) philosophy into
all our decision-making processes; from the strategic selection of greenfield exploration programs
through to responsible and sustainable resource development. This considers all our stakeholders,
their key issues, concerns and the how we go about our business.
To this end Alligator has developed its plan from a Stakeholder Perspective as
follows:
We aim to add value in all our decision-making for shareholders.
We wish to provide an engaging, challenging, enjoyable and respectful workplace for our
employees.
We respect the rights of landowners and communities and collaborate and negotiate
based on mutual benefit.
We respect the cultural heritage and connection to country of Traditional Owners and
wish to create mutually beneficial opportunities.
We aim to minimise our footprint on the environment. This will be achieved through
innovation, use of latest technology, and responsible adaptive land management
techniques.
To firmly embed this philosophy in the business, AGE continues to develop an ESG
framework that:
Considers material topics (for example, land and biodiversity management, Aboriginal
heritage, uranium and radiation, and local communities) relevant to an exploration and
development company, while leveraging international guidance such as the Global
Reporting Initiative (GRI).
Requires engagement and feedback with our stakeholders on a continuing basis to
understand their perspectives, shared values and outcome expectations, and
Drives our operating performance, informs strategy and identifies further actions for
implementation.
Alligator Energy 2025 Annual Report 25
AGE Governance framework
Alligator Energy acknowledges and respects that the topic of uranium is a sensitive issue for some
stakeholders. We will always work to better understand any concerns people have and provide
information about risks that may be posed by the commodity along with the development plans for
the project and the environmental protections that must and are being followed, to be as
transparent as possible.
As the Samphire Project advances through the study phase and Alligator evolves from an
exploration company to a developer, so our approaches and commitments to ESG need to expand.
We will continue to develop and deliver ESG outcomes which are fit for purpose and at a level
commensurate with community and other stakeholder expectations.
The following sections outline how we are putting our ESG philosophy into practice. Importantly,
our current activities undertaken at Big Lake (South Australia), Nabarlek North and Tin Camp
Creek (Northern Territory) are campaign based and by the very nature of exploration, short term.
This contrasts with the significant and ongoing activities at the developing Samphire Project (South
Australia). As a result, this report on current initiatives and practices focusses largely on delivery
of our ESG philosophy and outcomes at Samphire, with commentary on other portfolio projects, as
appropriate.
Shareholders
Team
Communities
Land Owners
Traditional
Owners
Focus on
Environment
Stakeholder
Perspective
Alligator Energy 2025 Annual Report 26
Environment
Samphire Uranium Project
(20km South of Whyalla, South Australia)
At Samphire, we are committed to collaborating with the immediate and surrounding landholders to
improve the quality of the land and local environment values to as close to pre-pastoral conditions
as possible, acknowledging that grazing has been ongoing for more than 130 years.
Demonstrating that mineral exploration/project evaluation and pastoral activities can successfully
co-exist and
Share your feedback
Discover