Retention Lease Approved - Samphire Field Recovery Trial
Released
Released
Announcement PDF
ASX Announcement
14 January 2025
Retention Lease Approved for Samphire Field
Recovery Trial
Alligator Energy (ASX: AGE, ‘Alligator’ or ‘the Company’) is pleased to confirm that a Retention
Lease for conducting the in-situ Field Recovery Trial (FRT) at the Samphire Uranium Project, near
Whyalla, South Australia has been granted.
Highlights:
• The Company has received confirmation from the Department for Energy and
Mining (DEM) of the grant of a Retention Lease (RL) for the conduct of the FRT,
incorporating a trial wellfield and pilot uranium extraction plant.
• The conditions attaching to the RL will be factored into the Program for
Environment Protection and Rehabilitation (PEPR) which forms the operating
plan for the FRT. The PEPR is targeted for submission by Alligator in late Jan /
Early Feb 2025.
• Approval of the PEPR represents the final step in the DEM regulatory process,
and with an EPA site permit process underway, these will allow commencement
of on-site construction of the FRT infrastructure.
• Fabrication of the FRT pilot process plant in Adelaide was completed in July
and the equipment is currently being stored in Whyalla.
• A preferred Whyalla based contractor has been selected to complete the on-site
construction activities including the civil works, pipework etc. Contract
negotiations for this work are currently being finalised to lock in a definitive
schedule of work and cost.
Alligator’s CEO Greg Hall stated: “Securing the Retention Lease for the Samphire pilot field
recovery trial is a major step forward for the Project. With the pilot plant and equipment already in
Whyalla and engagement of a construction group being finalised, post approval of the required
PEPR or operating plan and EPA permit, we are ready to construct and operate.
Alligator is already ramping up community engagement with the recent appointment of a full time
Stakeholder Engagement Manager and will be increasing its presence through the year in Whyalla
and at the Samphire site.
The FRT will provide the final operational parameters and inputs for a planned Definitive Feasibility
Study for the future Samphire Uranium Project.”
Field Recovery Trial Update
The Company has received formal advice from the DEM of the grant of a RL for the purposes of
conducting a field recovery trial at the Samphire Project. The Licence contains a number of
conditions covering (for example) stakeholder engagement processes; saline groundwater
management; soil, vegetation and fauna strategies; air quality criteria; radiation management;
traffic, noise and public safety. These conditions are being incorporated into the PEPR which will
be the document governing how the trial will be conducted.
Approval of the PEPR is the final step in the DEM regulatory process to commence on-site
construction of the FRT infrastructure, with an EPA site permit process also underway.
Fabrication of the containerised FRT plant by Adelaide Control Engineering was completed in July
2024 along with acceptance testing of the ion exchange and wellhouse modules. The pilot plant
and associated equipment is currently in Alligator’s Whyalla yard.
Contractual arrangements with a preferred Whyalla based contractor for the FRT civil works and
construction are being finalised based on a detailed scope of work, a targeted schedule and
definitive cost estimate. It is anticipated that the FRT construction will employ approximately 20-30
people from the Whyalla region over a 2-to-3-month period, with a lesser number for ongoing field
trial operations.
Recap of the objectives of the FRT
1. Designed to confirm key parameters of a future production operation and marks an
important step toward development.
2. Parameters to be assessed include in-situ chemistry, hydrogeology, uranium recovery,
reagent usage, and other environmental and economic factors.
3. Data and learnings further de-risk the Project and provide the necessary inputs to a
definitive feasibility study and Mining Lease Application to be commenced during 2H 2025.
The FRT operations will be conducted over a period of three to four months (targeted approximately
from the start of Q3 2025 (refer Fig 2 – Indicative Samphire FRT Schedule) and will involve
establishing three well-field patterns and placement and construction of a pilot processing plant
(already fabricated). Post completion of the FRT operations, and any additional testwork identified,
the pilot plant and wellfields will be removed and the area rehabilitated.
2
Fig 1 – Layout of the FRT production wellfields and pilot plant site.
3
Fig 2 – Indicative Schedule for Samphire Field Recovery Trial - PEPR approval, construction and FRT
operations – subject to Department of Energy and Mining (and Co-Regulators) approval of the PEPR as
estimated.
This announcement was authorised for release by the CEO and Managing Director.
4
Contacts
For more information, please contact:
Mr Greg Hall
Mr Mike Meintjes
CEO & Managing Director
Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
Forward Looking Statement
This announcement contains projections and forward-looking information that involve various risks and uncertainties
regarding future events. Such forward-looking information can include without limitation statements based on current
expectations involving a number of risks and uncertainties and are not guarantees of future performance of the
Company. These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ
materially from those expressed in the forward-looking information. Actual results and future events could differ
materially from anticipated in such information. These and all subsequent written and oral forward-looking information
are based on estimates and opinions of management on the dates they are made and expressly qualified in their
entirety by this notice. The Company assumes no obligation to update forward-looking information should
circumstances or management’s estimates or opinions change.
Competent Person’s Statement
Information in this report that supports plans for a field recovery trial is based on current and historic Exploration and
Resource Drilling Results compiled by Dr Andrea Marsland-Smith who is a Member of the AusIMM. Dr Marsland-Smith
is employed on a full-time basis with Alligator Energy as Chief Operating Officer, and has sufficient experience which is
relevant to the style of mineralisation and type of deposit under consideration (including 21 years in ISR uranium mining
operations and technical work) and to the activity she is undertaking to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr
Marsland-Smith consents to the inclusion in this release of the matters based on her information in the form and context
in which it appears.
5
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration, development and
operations of both uranium and nickel projects (both laterites and sulphides).