Commissioning of Pilot Plant Complete
Released
Released
Announcement PDF
ASX Announcement
17 February 2026
Highlights:
• Pilot plant to be energised, full operations team recruited and inducted, final
preparation for field recovery trial (FRT) operations now underway
• First test pattern pre-conditioning to commence next week in readiness for
uranium extraction
• FRT to run for circa four months with first results expected late March 2026
• Concurrent work streams progressing, including aggressive drilling programs
to commence at Samphire and Big Lake this quarter
Alligator Energy Ltd (ASX: AGE, ‘Alligator’ or ‘the Company’) is pleased to provide a
further update on the advancement of its Samphire Uranium Project, following the recent
announcement of practical completion for the construction of the FRT pilot plant. Since
practical completion, the Company has successfully completed both dry and wet
commissioning activities, in line with the project schedule and within the budget. These
activities have confirmed the operational readiness of the plant and mark the final technical
milestone ahead of commencing operations.
With the commissioning now complete, Alligator will proceed to energise the plant and
undertake final operational preparations. The full operations team has now been recruited
and inducted, ensuring the site is fully resourced and ready to transition into live operations.
The first test pattern pre-conditioning is targeted to commence next week in readiness for
uranium extraction, with the first meaningful field recovery results expected in late March.
The FRT is planned to operate for approximately four months and will generate a consistent
stream of operational and technical data over this period. The trial is designed to validate
recovery performance and operating parameters, supporting future development decisions
at Samphire.
In parallel with the FRT, Alligator will advance several value-accretive workstreams across
its uranium portfolio. These include an upgrade of the Samphire Mineral Resource Estimate
to incorporate the Plumbush satellite prospect, as well as the commencement of an
aggressive drilling programme at both Samphire and the Company’s Big Lake project
(weather permitting).
Together, these activities position Alligator for a period of sustained operational progress
and strong news flow through the coming months, as the Company moves from construction
and commissioning into active trial operations, resource growth, completion of a bankable
feasibility study, and mining lease permitting activities.
Commissioning of Samphire Pilot Plant Completed
2
Alligator’s CEO Andrea Marsland-Smith stated: “This is an exciting time for Alligator and
a milestone the team has been working towards for a number of years. Completing
commissioning in line with the schedule previously provided to the market bodes very well
for the next phase of the project and highlights the strength of our internal capabilities and
the quality of our team. With the plant ready to operate and a fully staffed site, we are now
transitioning into operations and field recovery. The coming months will be busy and highly
active, with the FRT, resource upgrades and expanded drilling programmes all underway
as we continue to build momentum across the business.”
This announcement was authorised for release by the Board of Alligator Energy Ltd.
Engage with this announcement at the Alligator Energy InvestorHub.
Figure 1: Samphire FRT Pilot Plant
3
Contacts
For more information, please contact:
Ms Andrea Marsland-Smith
CEO
Mr Joe Sutanto
CFO & Company Secretary
For media enquiries, please contact:
Jeffrey Sterlson
General Manager - Government Relations, Communications and Public Affairs
js@alligator energy.com.au
This announcement contains projections and forward-looking information that involve various risks
and uncertainties regarding future events. Such forward-looking information can include without
limitation statements based on current expectations involving a number of risks and uncertainties
and are not guarantees of future performance of the Company. These risks and uncertainties could
cause actual results and the Company’s plans and objectives to differ materially from those
expressed in the forward-looking information. Actual results and future events could differ materially
from anticipated in such information. These and all subsequent written and oral forward-looking
information are based on estimates and opinions of management on the dates they are made and
expressly qualified in their entirety by this notice. The Company assumes no obligation to update
forward-looking information should circumstances or management’s estimates or opinions change.
Alligator Energy is a uranium and energy metals project development and exploration group with
clear pathways for approval and development through its multi-jurisdictional portfolio. The Alligator
Energy Directors and Leadership Team have significant uranium experience including achieving
approval of WA’s first uranium mine at the Wiluna Uranium Project (Toro Energy), discovery and
pre-feasibility study of the Husab Uranium Mine in Namibia (Extract Resources) and management
roles with WMC Olympic Dam, ERA Ranger Mine and Heathgate Resources uranium ISR
operations at Beverley and Four Mile.