Quarterly Activities Report and 5B Cashflow - December 2024
Released
Released
Announcement PDF
QUARTERLY REPORT
FOR THE PERIOD ENDING
December 2024
3131December
2021
ASX: AGE
2
Quarter Highlights
Alligator Energy Limited (“Alligator”, “AGE” or the “Company”) is pleased to release the 31 December
2024 Quarterly Activities Report.
Significant Highlights for the Quarter include:
Samphire Project
•
•
•
•
•
•
The Company received the draft Retention Lease (RL) tenement documents on 18 December
from the SA Department for Energy and Mining (DEM) including the proposed Conditions of
operation with which the Company must comply during the Field Recovery Trial (FRT).
Alligator subsequently reviewed and accepted the Conditions, with DEM granting the Retention
Lease post quarter end on 13 January 2025.
The Conditions attaching to the RL will be factored into the Program for Environment
Protection and Rehabilitation (PEPR) which forms the operating plan for the FRT. The PEPR is
targeted for submission by Alligator in early Feb 2025.
Fabrication of the FRT pilot process plant in Adelaide was completed in July 2024 and the
equipment is currently being stored in Whyalla.
A preferred Whyalla based contractor was selected to complete the on-site FRT construction
activities including the civil works, pipework etc. Contract negotiations are currently being
finalised.
Drilling continued at Blackbush West extensions, with west and south extension areas
showing encouraging medium-high uranium grade intercepts. Along with this, key intercepts
in northeast extension drilling area showed that mineralisation has not yet been closed out.
Big Lake Project
•
•
•
Laboratory assays confirmed Alligator’s uranium discovery in its inaugural drilling program
last year, where significant thicknesses of anomalous uranium mineralisation were intersected
within interbedded palaeochannel sand units of the Namba Formation within EL6367 (refer ASX
release’s 13 August 2024 and 23 October 2024).
A heritage clearance was undertaken during the quarter to allow follow-up drilling in Q1 2025.
Exploration PEPR submitted to cover continued drilling works across EL6367.
Nabarlek North Project and region
•
•
•
•
Drilling program of 22 holes for a total of 3,526 m completed. This included step-out drilling
around northern extensions to the U40 Prospect.
Finals assays pending for the above program, though field observations suggest only minor,
sub-economic intercepts of uranium were encountered.
Significant reconnaissance mapping and sampling undertaken across the tenement holding,
particularly in northern sections, where limited work has occurred in the past.
Work undertaken on ground truthing previously identified high priority targets at the Tin Camp
Creek Project.
Corporate and Uranium Market
•
•
•
•
Cash balance at quarter end of $20.2 M.
Terms of a Deed of Variation to the EnviroCopper Limited (ECL) Shareholders’ Agreement were
finalised. Post quarter end, a subscription involving a further $871k investment was completed.
Alligator now holds a 15.6% interest in ECL and has appointed Greg Hall to the ECL Board.
30M Performance Shares issued to the vendors of the Big Lake Uranium Project in 2020 lapsed
and were cancelled as the Discovery Milestone was not met.
The spot U3O8 price ended the quarter at $72/lb (Sept 2024: $82/lb)
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 2 of 20
3
•
•
The term U3O8 price dropped slightly to US$79lb U3O8.
Tech and datacentre companies and their expanding relationships with current and future
nuclear power suppliers dominated the market headlines during the quarter.
Post quarter end there was significant news regarding the Kazak / Cameco Inkai JV project
temporary halting production, but this was resolved. Also, news of the Chinese developed
DeepSeek AI technology benefits impacted US tech and nuclear stocks, again the situation
seeming to be stablising.
•
Plans for the forthcoming quarter:
•
Samphire
- Submission of a PEPR (the operating plan) for field recovery trial operations.
- Contractual finalisation with preferred Whyalla based construction contractor for pilot plant site
establishment.
- Continued work on certain optimisation studies (water, power, transport, logistics etc.) required to be
concluded prior to commencement of a feasibility study in 2H 2025.
•
Big Lake
-
•
Nabarlek North / ARUP
-
•
Exploration PEPR approval.
Commence follow-up drilling program to test discovery area and other locations for fertile
stratigraphy.
Data integration of assays, 2024 drilling results and petroleum drilling data to refine mineralisation
model for further drilling programs on EL6367.
Review of multi-elemental assays from drilling data once all received.
Review of all new 2024 data to assess remaining prospectivity.
Preliminary planning for potential 2025 program.
Piedmont
- Continued marketing of the opportunity to acquire the Piedmont Project as the Company prefers to
focus on uranium exploration and development and applications for the in-situ recovery (ISR) mining
technique.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 3 of 20
4
Samphire Uranium Project Development
• The Company received the draft Retention Lease (RL) tenement documents from the SA
Department for Energy and Mining (DEM) including the proposed Conditions of operation with
which the Company must comply while operating the Field Recovery Trial (FRT).
• Alligator reviewed the Conditions and after clarification of some points, accepted the Conditions
on 30 December 2024. The Company received confirmation from the DEM of the grant of a RL
for the conduct of the FRT, on 13 January 2025. The associated Conditions are now being
factored into the Program for Environment Protection and Rehabilitation (PEPR) which forms
the operating plan for the FRT. The PEPR is targeted for submission in Jan / early Feb 2025
and will likely take some months to be approved.
• Approval of the PEPR will represent the final step in the regulatory process, allowing
commencement of on-site construction of the FRT infrastructure.
• Contractual arrangement negotiations commenced with a preferred Whyalla based contractor
for the FRT civil works and construction based on a detailed scope of work, a targeted schedule
and definitive cost estimate.
• Drilling activities continued during the quarter. Key outcomes (ASX release 21 Nov 24) include:
-
Uranium mineralisation extended by a cumulative 500m of strike length outside the known
Blackbush West Mineral Resource Envelope.
-
Significant uranium intersections encountered in roll fronts focussing on the western and
southern areas of Blackbush west.
o A total of 61 holes drilled for 5,158m from mid-July to mid November 2024.
o Results align with the strategy outlined in Alligator’s Exploration Target Range 1.
-
Continued refinement in understanding of the Blackbush West uranium roll fronts has delivered
further targets outside of the Inferred mineral resource.
-
Significant uranium mineralisation intersections include (see Figure 1 for full detail):
o
o
o
o
o
o
o
o
o
•
BBRM24-304
BBRM24-278
BBRM24-338
BBRM24-321
BBRM24-282
BBRM24-283
BBRM24-318
BBRM24-330
BBRM24-314
1.3 meters at 1.94% (19,391ppm) pU3O82 from 62.6m (GT 25,208)3
1.1 meters at 0.44% (4,392ppm) pU3O8 from 62.94m (GT 4,832)
2.4 meters at 0.20% (1,948ppm) pU3O8 from 56.7m (GT 4,675)
1.1 meters at 0.36% (3,633ppm) pU3O8 from 58.59m (GT 3,996)
1.7 meters at 0.23% (2,314ppm) pU3O8 from 63.1m (GT 3,934)
0.8 meters at 0.45% (4,506ppm) pU3O8 from 65.03m (GT 3,604)
0.7 meters at 0.36% (3,566ppm) pU3O8 from 59.1m (GT 2,497)
0.8 meters at 0.18% (1,791ppm) pU3O8 from 63.1m (GT 1,433)
0.6 meters at 0.17% (1,734ppm) pU3O8 from 59.14m (GT 1,040)
An update of the JORC Mineral Resource Estimate, inclusive of the January to November drill results4
to be completed in Q1, 2025, targeting both resource expansion and category conversion from inferred
to indicated.
1 AGE ASX Release 7 December 2023, Significant Exploration Target Range established, Samphire Uranium Project 02751150.pdf
2 Note: pU O
3
8 denotes that the grade has been determined by Prompt Fission Neutron downhole logging
3 GT= grade(ppm) x thickness(m) – divide by 10,000 for m% GT
4 ASX release 1 May 2024 – Extension of Uranium Mineralisation at Samphire, 02801940.pdf
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 4 of 20
5
Figure 1: Q4 drilling at the Samphire Project. Intercepts above 250ppm pU3O8 (yellow dots), 100ppm-250ppm pU3O8
(red dots) and <100ppm pU3O8 (blue dots). The orange dashed channel outline is the latest channel boundary validated
by drilling, compared to the green–grey palaeochannel interpretation from ground gravity.
Big Lake Uranium (BLU) Project
•
As per ASX release 23 October 20245, drilling at Site 10 on EL6367 returned significant thicknesses of
paleochannel sands and elevated uranium values, and these have now been confirmed by assay (refer
Table 1). Four holes recorded uranium values at over 100 ppm, including two intersections within porous
sands of greater than 20 m thickness (refer Figure 2 & 3 and the table below).
•
A heritage clearance was undertaken in late October with the Yandruwandha Yawarrawarrka Traditional
Land Owners Aboriginal Corporation for additional site clearances for a 2025 drilling program.
5 AGE ASX Release 23 October 2024, Assay Results from the Big Lake Uranium Project confirm Significant Uranium Discovery.
https://wcsecure.weblink.com.au/pdf/AGE/02870056.pdf
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 5 of 20
6
Hole ID
From (m)
To (m)
Thickness
(m)
Laboratory Assay
(U ppm)
AC24-021
106
126
20
100
AC24-021
129
130
1
129
AC24-022
93
128
35 **
117
AC24-023
104
109
5
47
AC24-025
108
118
10 m
138
Table 1: Assay results confirming previously announced estimates - ** previously believed to be a 5m intercept,
AGE ASX Release 13 August 2024
Figure 2: Alligator’s significant tenement holding over the southern Cooper Basin which comprise the Big Lake Project.
Area of current AGE drilling activities and location Site 10 denoted.
•
The proposed 2025 drilling program will now include the use of a mud-rotary drill rig to allow for
acquisition of downhole geophysics and to test the Eyre Formation that underlies the Namba
Formation up to 400 m below surface. These largely uncemented and semi-consolidated sediments
of the Eyre Formation are a principal host for uranium mineralisation in the nearby Frome Embayment
district.
•
Alligator is currently in the process of finalising approvals for follow-up drilling commencing Q1 2025.
Additional drill lines are also planned to use aircore drilling to test other locations for fertile stratigraphy
and interpretated paleochannels.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 6 of 20
7
Figure 3: Drillhole location map (Site 10) showing uranium grades (ppm) and thicknesses from laboratory assay results.
Alligator Rivers Uranium Province (ARUP)
Exploration progress for the quarter includes:
•
Finalisation of 2024 drilling program at Nabarlek North through sampling of all drill holes and
environmental remediation completed. A total of 504 downhole samples were taken for Geochemical
analysis across varying geological, alteration and potentially mineralised zones. All samples are
anticipated early Q1 2025 and will inform 2025 planning workshops and future targeting.
•
In addition to downhole sampling, 236 surface samples were taken across the Nabarlek North project
forming broad traverses designed to aid with geological interpretations and identify the most
prospective geological domains with the project.
•
At the Company’s Tin Camp Creek Project hosting the historic Caramal resource, 88 surface samples
were taken across historic and new prospects in conjunction with environmental access assessments
which will inform the company’s 2025 program generation for the project.
•
Completion and submission of two Co-Funding applications to the NT Government. These grants have
contributed to the funding of 2024 Airborne geophysics and greenfields exploration RC drilling.
Claimable Co-funding expenditure has confirmed the company will receive in excess of $175k in grants
against the 2024 ARUP exploration program with first 50% now received.
•
Demobilisation of drilling, Fly Camp and site closure completed pre wet season following weeds
programs in November, in collaboration with local ranger groups.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 7 of 20
8
Piedmont Nickel Cobalt Project - NW Italy (Ni, AU, Cu, Co – AGE: 51% JV)
•
Tenement applications approved - Castello di Gavala, Sella Bassa and Valmaggia applications
covering a total area of 5,405 hectares were approved and the licences issued during the quarter. The
applications were resubmitted during 2024 with refined boundaries targeting the key lower mantle
geological settings hosting Ni, Cu, Au and Pt-Pd occurrences. At the time of assessing data for the
resubmission of the applications, the presence of carbonatites within the sequence was identified
providing the opportunity to also investigate the potential for REE occurrences. Current granted
tenement outlines are shown below in Figure 4.
•
A small stream sampling program was undertaken during the quarter at the Laghetto and Sella Bassa
licences proximal to the Gula Prospect. The objective of this program was to follow up on the
exceptional Au grab samples results (up to 60.8g/t – ASX Announcement- 14 September 2018) and
historic stream sampling to investigate the extent of the Au anomalism. A total of 5 samples were
collected spanning approximately 2km of river system. Bulk samples were split into 3 fractions for each
site giving a total of 15 samples now submitted to ALS Ireland for geochemical analysis. Assaying will
cover a suite of elements including Au, Ni and REEs.
•
Marketing of the Project to interested parties will resume once the assay results for the recent sampling
program are returned and the Project Information Memorandum updated.
Figure 4. Piedmont granted tenements. Alpe Laghetto previously granted and the now approved Sella Bassa,
Valmaggia and Gavala tenements.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 8 of 20
9
Investment in EnviroCopper Limited (ECL) – Cu ISR
AGE: 7.8% at 31/12/24
•
Activity at the Kapunda Project during the quarter covered continued planning and preparation for the
Site Environmental Lixiviant Test (SELT) Circulation Trial (copper extraction) whilst awaiting the
regulatory approval in the form of a Program for Environment Protection and Rehabilitation (PEPR)
including:
Commissioning of the SELT plant and equipment.
Continuation of the groundwater monitoring program.
Independent review of the hydrogeological data.
•
Activity for the Alford West Project included receipt of the independent hydrological report for the three
wells (2 injector and 1 extractor) drilled in the previous quarter noting that:
Groundwater salinity is high with recorded EC values in the range 30,000 to 40,000 µS/cm.
The water level responses to the pump testing are strongly anisotropic confirming geological
interpretation of predominant fracture system running East-West.
Further drilling and hydrological studies are planned to commence in March 2025
•
ECL is in ongoing investment discussions with international investors focused on copper ISR for a
significant equity injection.
•
See Corporate Section below regarding finalisation, post quarter end, of the originally envisaged Stage
1 funding subscription resulting in an increase in the ECL equity interest from 7.8% to 15.61%
Market Update
•
The spot U3O8 price ended the quarter down at ~US$72/lb [September 2024 – US$82/lb] and the
UxC term price indicator reduced US$2/lb to US$79/lb U3O8 for the month of December 2024, the
first step-down in term price since September 2022.
Key market drivers by both Governments and big technology companies during the quarter were:
US:
•
Amazon expanded its nuclear ambitions by pledging $334 million towards studying the feasibility of a
Small Modular Reactor (SMR) project. The initial plan targets 320 megawatts using 4 SMRs, with
potential growth to 12 units, building on their earlier partnership with Dominion Energy and Energy
Northwest.
•
At the COP 29 climate conference, the United States announced an ambitious goal to triple its nuclear
power capacity by 2050, driven by growing energy demands from AI and digital infrastructure. The
DOE noted in December that data centre power consumption has tripled in the past ten years and
could triple again by 2028.
•
The incoming U.S. President Trump's appointment of Chris Wright to head the Department of Energy
appears to suggest a potential policy shift favouring nuclear power expansion, alongside oil and gas
development, to address increasing energy needs from AI and EVs
•
Small Modular Reactor start up, Deep Fission, has partnered with Endeavour Energy to deploy up to
2.0 GWe of nuclear capacity for data centres, with initial reactors set to begin by 2029.
•
In response to potential U.S. tariffs Canada is considering countermeasures including tariffs, export
controls, and taxes on uranium and other key resources.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 9 of 20
10
•
Post quarter end, news of the Chinese DeepSeek AI technology being substantially cheaper to
develop sent an equity market shock to US tech companies, along with nuclear companies and
uranium equities. However in late January this seemed to be stablising.
Asia
•
Russia has issued a decree on new restrictions on enriched uranium product exports to the United
States, now requiring special case-by-case approval from their technical export control authority.
•
Kazatomprom reported a significant shift in their sales distribution, with Chinese customers now
accounting for about 48% compared to 38% previously, while U.S. sales have decreased.
•
Kazatomprom suspended production at Inkai’s block No. 1 due to delays in obtaining approvals under
Kazakhstan’s Subsoil Code. The JV, where Cameco holds 40%, plans to resolve the issue quickly,
expecting minimal impact on 2025 production. Inkai is Kazatomprom's largest mine, producing 7.7
MMlbs in 2023. (re-start of the Inkai mine has since been reported in Jan 2025).
•
Japan's incoming Prime Minister has revised his stance on nuclear power, now advocating for it as
part of an "optimal" energy mix, targeting 20% nuclear power by 2040 alongside 40-50% renewable
energy.
•
The Japanese power utility Chugoku Electric Power announced that the 789 MW Shimane nuclear
power plant will resume commercial operations in January 2025.
•
Cloud gaming company Ubitus K.K. plans to construct a data centre near a Japanese nuclear facility,
citing nuclear power's reliability and cost-effectiveness for meeting AI and cloud computing's energy
requirements.
Europe:
•
The UK government announced plans to establish "AI Growth Zones" powered by sustainable energy,
including Small Modular Reactors. By 2030, it aims to increase public AI computing capacity 20-fold,
with over $17 billion in investments from Vantage Data Centers and Nscale (tech company),
emphasizing nuclear energy’s role in sustainable, competitive AI innovation.
•
The Dutch government has expanded its nuclear ambitions to include four new reactors, twice its
original plan, while Switzerland is working to modify its 2018 nuclear plant ban to ensure energy
security if renewable targets aren't achieved.
•
Poland has approved $14.7 billion in funding for its first nuclear power plant, featuring three AP1000
reactors, set to replace coal plants by 2036. The project’s financing will include 30% equity and debt
from the US Export-Import Bank.
Corporate
•
•
During Cash balance at quarter end of $20.2M.
•
After obtaining approval from Shareholders at the 2024 AGM, the Company granted 14.4M Director
Options to the non-executive directors as part of their remuneration arrangements. The options vest
based on continuing service in three equal annual tranches commencing October 2024. Details of the
further terms and conditions attaching to the Director Options was set out in the AGM Notice of
Meeting.
•
Further to the update in the September 2024 Quarterly, the Company has finalised the terms of a
Deed of Variation to the EnviroCopper Limited (ECL) Shareholders’ Agreement involving:
Completion of the originally envisaged Stage 1 investment (see ASX Announcement 18
December 2023) through the further subscription for 321,405 shares in ECL for a consideration
During the quarter the Company issued 24.6M short- and long-term incentive zero-strike priced options
(on a 50:50 basis) to eligible employees (including Key Management Personnel). The options only
vest based on an annual assessment against stretch target KPIs set for each individual (STIs) for
FY25 or the generation of shareholder value-add triggers (LTIs) over a three-year period.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 10 of 20
11
•
of $871,007. The subscription arrangements were completed post quarter end. Alligator now
holds a 15.61% interest in ECL.
Confirming that Alligator’s further sole funding rights set out in the 18 December 2023 release will
lapse; and
The right for the Company to appoint a representative to the Board of ECL.
On 4 December 2024, 30M Performance Shares issued to the vendors of the Big Lake Uranium Project
lapsed and were cancelled as the milestone of defining a JORC Complaint Inferred Resource of
25mlbs U308 at 1,000ppm or greater was not met.
Capital Structure and Listing Rule 5 disclosures
At 31 December 2024, the Company had the following capital structure and cash balances:
As at 31 December 2024
Cash Balance
A$20.2M
Ordinary Fully Paid Ordinary Shares (AGE)
3,873.6M
Listed Options 7.8c (Exp 28/11/25) (AGEOC)
273.9M
Unlisted Options 8.1c (Exp 01/12/25)
132.0M
Unlisted Employee Incentive Performance Options
41.9M
Director Share Options
14.4M
Expenditure on exploration and evaluation activities during the December 2024 quarter totalled $2,691k
(previous quarter - $3,640k) and related principally to advancing the Samphire Project, preparing for a follow
drilling program at Big Lake in 1Q 2025 and finalisation of the 2024 field program at the Nabarlek North and
Tin Camp Creek Projects in the Alligator Rivers.
Payments to related parties including non-executive director fees and the salary of the CEO and Managing
Director for the December quarter totalled $123k (previous quarter $128k).
This announcement has been authorised for release by the CEO and Managing Director.
Contacts:
For more information, please contact:
Mr. Greg Hall
Mr. Mike Meintjes
CEO & Director
CFO & Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 11 of 20
12
Competent Person’s Statement
Uranium
The information in this announcement that relates drillhole data, QAQC and geology aspects related to the Alligator projects
is based on and fairly represents information provided by Dr Andrea Marsland-Smith who is a Member of the AusIMM. Dr
Marsland-Smith is employed on a full-time basis with Alligator Energy as Chief Operating Officer, and has sufficient
experience which is relevant to the style of mineralisation and type of deposit under consideration (including 21 years in
ISR uranium mining operations and technical work) and to the activity she is undertaking to qualify as a Competent Person
as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves. Dr Marsland-Smith consents to the inclusion in this release of the matters based on her information in the form
and context in which it appears.
In relation to Exploration results referred to in this Quarterly report, the Company confirms that it is not aware of any new
information or data that materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply
and have not materially changed. In relation to production target referred to in AGE ASX release 14 December 2023 that
is relevant for underpinning the field recovery trial at Samphire, the Company confirms that all material assumptions
underpinning the production target, and the forecast financial information derived from the production target, in the initial
announcement continue to apply and have not materially changed.
The information in this report that relates to the Blackbush Mineral Resource estimate (uranium) is based on and fairly
represents information compiled by and generated by Mr Ingvar Kirchner, AMC Geology Manager (Perth) and a full-time
employee of AMC Consultants. Mr Kirchner is a Fellow of the Australasian Institute of Mining and Metallurgy (the AusIMM)
and a Member of the Australian Institute of Geoscientists (the AIG). Mr Kirchner has sufficient experience relevant to the
style of mineralisation and type of deposit under consideration and to the activity which is being undertaken to qualify as a
Competent Person as defined by the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (the JORC Code).
Forward Looking Statement
This announcement contains projections and forward-looking information that involve various risks and uncertainties
regarding future events. Such forward-looking information can include without limitation statements based on current
expectations involving a number of risks and uncertainties and are not guarantees of future performance of the Company.
These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ materially from
those expressed in the forward-looking information. Actual results and future events could differ materially from anticipated
in such information. These and all subsequent written and oral forward-looking information are based on estimates and
opinions of management on the dates they are made and expressly qualified in their entirety by this notice. The Company
assumes no obligation to update forward-looking information should circumstances or management’s estimates or opinions
change.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 12 of 20
13
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally through its equity interest and funding agreement with EnviroCopper Limited. Alligator’s Directors have
significant experience in the exploration, development and operations of both uranium and nickel projects (both laterites
and sulphides).
Projects
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 13 of 20
14
Alligator Group Tenure Holdings at Quarter End:
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 31 December 2024.
ARUP (NT) Uranium
Licence Number
Tenement
Ownership
Interest
EL24922
EL25002
Tin Camp
Creek
Tin Camp
Creek
Tin Camp
Creek
State
Status
(km2)
Name
EL24921
Area
TCC Project P/L
98
76.79
NT
Granted
TCC Project P/L
98
194.59
NT
Granted
TCC Project P/L
100
11.55
NT
Granted
EL24291
Beatrice
Alligator Energy Ltd
100
337.21
NT
Granted
EL26796
Beatrice
Alligator Energy Ltd
100
19.77
NT
Granted
EL27252
Nabarlek North
100
6.75
NT
Granted
EL27253
Nabarlek North
100
5.61
NT
Granted
EL28389
Nabarlek North
100
110.83
NT
Granted
EL28390
Nabarlek North
100
33.58
NT
Granted
EL29991
Nabarlek North
100
26.87
NT
Granted
EL29992
Nabarlek North
100
63.81
NT
Granted
EL29993
Nabarlek North
100
57.06
NT
Granted
EL31480
Nabarlek North
100
188.44
NT
Granted
100
123.88
NT
Application
100
907.44
NT
Applications
EL26793, EL26794,
EL26795
Beatrice
Northern Prospector
P/L
Northern Prospector
P/L
Northern Prospector
P/L
Northern Prospector
P/L
Northern Prospector
P/L
Northern Prospector
P/L
Northern Prospector
P/L
Northern Prospector
P/L
Alligator Energy Ltd
EL27777, EL27778,
EL28176, EL28293,
EL28315, EL28863,
EL28864, EL28865,
EL28950, EL31452,
Various
Northern Prospector
P/L
EL31453, EL31454,
EL32075, EL32389,
EL32390, EL32391
Eyre Peninsula (SA) Uranium
EL5926
Samphire
S Uranium Pty Ltd
100
332
SA
Granted
EL6350
Samphire
S Uranium Pty Ltd
100
38
SA
Granted
EL6835
Samphire
S Uranium Pty Ltd
100
61
SA
Granted
EL6901
Samphire
S Uranium Pty Ltd
100
119
SA
Granted