Commencement of Uranium Extraction for Samphire FRT
Released
Released
Announcement PDF
ASX Announcement
23 March 2026
Highlights:
• Field Recovery Trial (FRT) test pattern pre-conditioning successfully completed
• Introduction of reagents for uranium extraction from the first FRT test pattern has been
initiated, with first uranium observed coming into the plant
• Pilot plant operating as designed following completion of commissioning
• FRT progressing as planned with operational and recovery data to be generated over
the coming months
Alligator Energy Ltd (ASX: AGE, ‘Alligator’ or ‘the Company’) is pleased to provide an update on
the advancement of its Samphire Uranium Project, following the successful completion of
commissioning activities. The first test pattern pre-conditioning has been achieved, and the Company
has initiated the introduction of reagents which forms the lixiviant for extraction of uranium-bearing
solution (pregnant liquor solution – PLS) from the first trial wellfield, marking the commencement of
uranium extraction operations at Samphire. Although not yet at target extraction, it can be observed
that there are initial concentrations of uranium in the PLS flowing into the plant.
The preconditioning and commencement of recovery of uranium bearing solution represents an
important milestone in the FRT programme. The FRT is designed to operate for approximately four
months and will generate a consistent stream of operational and technical data. This will provide
critical information on uranium recovery performance, operating parameters and wellfield behaviour,
which will directly feed into the Company’s Bankable Feasibility Study that is currently underway.
The pilot plant, wellfield infrastructure and well flow rates are performing as designed and are
consistent with expectations for this stage of the trial. During the coming months, the Company will
continue to monitor wellfield performance, lixiviant solution chemistry, and uranium extraction rates
with the first meaningful recovery data expected to be reported in the coming weeks.
In parallel with the FRT programme, Alligator continues to advance several value accretive
workstreams across its uranium portfolio. These include progressing the Samphire Mineral Resource
Estimate upgrade (incorporating the Plumbush satellite prospect) and commencing aggressive
drilling programmes at both Samphire and the Company’s Big Lake project (weather permitting).
Together, these activities position Alligator for a period of sustained operational progress and strong
news flow as the Company advances Samphire through field recovery trials, resource growth,
feasibility study workstreams and mining lease permitting activities.
Commencement of Uranium Extraction at
Samphire Field Recovery Trial
2
Alligator’s CEO Andrea Marsland-Smith stated: “This is another milestone for the Samphire
project and reflects the consistent progress the team has made in systematically advancing and de
risking the project. The start of uranium extraction is an exciting step towards further confidence in
the project’s development pathway, particularly when the deposit is responding well to the in-situ
recovery process in these early stages of the trial”.
This announcement was authorised for release by the Board of Alligator Energy Ltd.
Engage with this announcement at the Alligator Energy InvestorHub.
Figure 1: Samphire Field Recovery Trial Plant in full operation (view looking north)
3
Contacts
For more information, please contact:
Ms Andrea Marsland-Smith
CEO & Managing Director
Mr Joe Sutanto
CFO & Company Secretary
For media enquiries, please contact:
Jeffrey Sterlson
General Manager - Government Relations, Communications and Public Affairs
js@alligatorenergy.com.au
This announcement contains projections and forward-looking information that involve various risks
and uncertainties regarding future events. Such forward-looking information can include without
limitation statements based on current expectations involving a number of risks and uncertainties
and are not guarantees of future performance of the Company. These risks and uncertainties could
cause actual results and the Company’s plans and objectives to differ materially from those
expressed in the forward-looking information. Actual results and future events could differ materially
from anticipated in such information. These and all subsequent written and oral forward-looking
information are based on estimates and opinions of management on the dates they are made and
expressly qualified in their entirety by this notice. The Company assumes no obligation to update
forward-looking information should circumstances or management’s estimates or opinions change.
Alligator Energy is a uranium and energy metals project development and exploration group with
clear pathways for approval and development through its multi-jurisdictional portfolio. The Alligator
Energy Directors and Leadership Team have significant uranium experience including achieving
approval of WA’s first uranium mine at the Wiluna Uranium Project (Toro Energy), discovery and
pre-feasibility study of the Husab Uranium Mine in Namibia (Extract Resources) and management
roles with WMC Olympic Dam, ERA Ranger Mine and Heathgate Resources uranium ISR
operations at Beverley and Four Mile.
About Alligator Energy
Forward Looking Statement
Share your feedback
Discover