Quarterly Activities Report and 5B Cashflow - June 2023
Released
Released
Announcement PDF
QUARTERLY REPORT
FOR THE PERIOD ENDING
30 June 2023
31 December
2021
ASX: AGE
Quarter Highlights
Alligator Energy Limited (“Alligator”, “AGE” or the “Company”) is pleased to release the 30 June 2023 Quarterly
Activities Report.
Uranium
Samphire Project
•
Samphire Uranium Project drilling operations continued during the quarter with a second drill rig onsite
from May 2023. Resource infill, resource extension and water sampling test drilling will extend through
to end of September 2023.
•
Further significant resource related drilling results were released during the quarter (ASX: 8 June 2023),
with a JORC Mineral Resource Estimate (MRE) update scheduled post drilling (Q4 2023), targeting an
increase in both the Indicated Category and the overall Estimate.
•
In parallel, the Scoping Study released in March 2023 will be updated, targeting an increased production
schedule (currently 1Mlbs pa) and life of mine (currently 12 years including ramp up / ramp down).
•
The South Australian Department for Energy and Mining (DEM) advised that the Retention Lease
application to enable operation of the Field Recovery Trial (FRT) had been accepted for assessment.
Some final water sampling information has recently been added to the application. The assessment is
now underway, with an anticipated public review and submission period to commence shortly. AGE will
then formulate responses to submissions ahead of finalising the required approval.
•
Process chemistry and engineering design for the FRT is being finalised, with ordering of key items and
components well advanced. A total of $615,000 has been committed for long lead items and other
equipment, including all the required resin for the IX plant.
•
The increased pace and quantum of activity at Samphire can be credited to the ISR experienced team
assembled by Dr Andrea Marsland-Smith, our COO, and this has been further enhanced with
commencement of a full time ISR credentialled Process Chemist, and engagement of ammjohn Pty Ltd,
a Project Engineering and Management group, to assist with management of the FRT trial.
•
Higher than usual autumn and winter rains have impacted drilling of the FRT monitor wells with a knockon effect anticipated for the Retention Lease approval timeframe. While the FRT plant infrastructure has
commenced offsite fabrication, we anticipate installation at Samphire will be delayed until Q1 2024
(subject to regulatory approval), with FRT operations commencing that Quarter. Minimal impact to the
overall development schedule for Samphire (as outlined in our Scoping Study release – ASX: 14 March
2023) is expected, as the planned Feasibility Study is due to commence during Q2 2024.
Big Lake Project
•
A Native Title Agreement for Mineral Exploration with the Yandruwandha Yawarrawarrka Traditional
Landowner Aboriginal Corporation (YYTLOAC) was executed on 6 May 2023, allowing for detailed
planning of an inaugural investigative drilling program at Big Lake.
•
A Program for Environmental Protection and Rehabilitation (PEPR) for the proposed 2023 field
exploration program was submitted in late June for approval.
•
Post quarter end, initial cultural heritage clearances were undertaken, and subject to final drill site
clearance, regulatory approvals and weather, drilling is then anticipated in late 2023.
Nabarlek North Project
•
Twenty-three (23) priority target areas have been identified for the focus of field work at Nabarlek North
(Alligator Rivers, NT) which commenced in early July 2023.
•
An induced polarisation (IP) geophysical survey over key areas covering a collective 20km2 is now
underway. Higher resolution follow-up is then anticipated over the best geophysical targets from this
work. A key objective of the IP survey is to map chargeability and subtle conductive structures in the
area north of DevEx Resources’ (ASX: DEV) high-grade U40 Prospect.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 2 of 22
•
Up to 1800 aircore/reverse air blast drill-holes are planned to be drilled in Q3 2023 to continue
geochemical and geological basement mapping to complement AGE’s 2022 work. The drill contractor
is now onsite.
•
The geochemical work has been designed both to determine / confirm the underlying geology, plus
determine the presence of potentially economically interesting minerals which may be present in the
overlying ionic clays, e.g. Rare Earth Elements.
Energy Minerals - Piedmont Project (Ni Cu Co)
•
In conjunction with AGE’s local geological specialists, site mapping and sampling was conducted in May
2023 across the EM conductors identified in 2022 at La Balma and Alpe Laghetto (Piedmont, Italy). In
addition, the Team assessed logistics for a potential 2024 drilling program, should the geochemistry
results provide compelling evidence for untested, mineralised targets below surface. Results from the
field visit are expected to be received late July/early August 2023.
•
The Company has agreed a three-month extension to the 12-month buyout option with Chris Reindler
and Partners (ASX release: 17 May 2022) until August 2023, in exchange for sole funding the recent
field work.
Corporate
•
•
•
Cash balance at quarter end of $18.5M.
Bell Potter initiated research coverage on Alligator with the release of their initial research report.
Significant progress has been made in the first two years of a strategic relationship with Traxys North
America LLC (Traxys), the U.S. arm of the global commodities trading group Traxys. Traxys is providing
uranium marketing services for future uranium production long-term offtake contracting, will consider
potential support in project development financing, and is assisting in uranium and energy minerals
project acquisition opportunities.
Plans for the forthcoming quarter:
•
Samphire – continue with monitor well installation and off-site procurement and construction for the
FRT; ongoing resource drilling at the Blackbush deposit focused on resource upgrade and extension
ahead of a planned JORC Mineral Resource Estimate and Scoping Study update early in Q4 and
finalising the regulatory approvals for the FRT.
•
Big Lake – cultural heritage survey over the proposed locations of an inaugural drill program along with
drilling contractor negotiations.
•
Nabarlek North – completion of both an IP survey and ongoing aircore/reverse air blast drilling program
over twenty-three (23) priority target areas identified from our work in 2022.
•
Piedmont – analysis of the assay results from the rock chip sampling in May 2023 at the La Balma and
Alphe Laghetto prospects and re-interpretation with the ground EM data obtained in 2022.
Uranium Market
•
Spot uranium price just over US$55 per lb at quarter end which is a US$5 per lb increase from the March
quarter end. At time of writing spot price is at US$56.15.
•
AGE attended the World Nuclear Fuel Market (WNFM) Conference in Europe with our marketing agent
Traxys. Meetings were held with many European and North American nuclear utilities who attended,
some of these now the third time Alligator has met with certain utilities. As advised in previous ASX
updates, AGE / Traxys have identified a few potential anchor utilities who are willing to negotiate earlystage conditional offtake contracts for a portion of future sales. We would see these discussions
advancing as we progress our Field Recovery Trial and enter into a Feasibility Study for Samphire during
2024.
•
At the WNFM conference, key uranium producers and near producers stated publicly that they are only
willing to increase production further on the basis of firm long-term supply contracts at higher level
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 3 of 22
pricing that will support the required returns and increased capital costs of that production. Coming on
top of the previously identified shortage of enrichment and conversion services, the pressure on
increased nuclear fuel prices is becoming obvious.
•
As of March 2023, 57 reactors were under construction around the globe, with 22 of those being in
China. During 2022, 6 new reactors were connected to the grid at an average capacity of 1,131MWe
(total capacity 9,054MWe) and 5 old reactors were shut down (total capacity 3,271MWe). Thus far in
2023, 4 new reactors have been connected to the grid in Slovakia, China, USA and Belarus (total
capacity 3,772MWe) and 5 old reactors have been shut down in Taiwan, Belgium and Germany (total
capacity 6,048MWe).
•
Small Modular Reactors (SMR) remain in the headlines, with an MOU signed with NuScale in Romania,
collaboration between France and Belgium on EDF’s NUWARD SMR design, a Rolls Royce/Sumitomo
study showing the potential for a 470 Mwe SMR design to support the UK’s hydrogen network and
Slovakia’s utility signing agreement in support of SMR development amongst other news on this front.
Samphire Uranium Project Development
Resource Drilling
Drilling operations in the current Blackbush JORC Mineral Resource envelope continued during the quarter. A
three-week field break in late April / early May to enable the pastoralist to manage their lambing season, and
several rain events sporadically prevented access to site during June.
A total of 42 holes were drilled during the quarter for a total of 3,582.5m, focussing on:
• Close-spaced in-fill drilling to 25m to finalise locations of the field recovery trial test wellfields
(Blackbush East and West) where multiple mineralised roll fronts were intersected. Significant grade
intercepts include (Figure 1):
Blackbush East
o
o
o
o
1.78 metres at 0.45% (4,569ppm) pU3O8 from 61.70 metres (GT 8,132)
1.94 metres at 0.11% (1,106ppm) pU3O8 from 58.20 metres (GT 2,145)
1.26 metres at 0.19% (1,916ppm) pU3O8 from 58.76 metres (GT 2,414)
1.30 metres at 0.21% (2,149ppm) pU3O8 from 60.72 metres (GT 2,793)
Blackbush West
o
o
o
o
1.08 meters at 0.13% (1,338ppm) pU3O8 from 75.02 metres (GT 1,445)
1.12 metres at 0.26% (2,696ppm) pU3O8 from 73,95 metres (GT 3,019)
1.58 metres at 0.10% (1,097ppm) pU3O9 from 77.44 metres (GT 1,733)
1.92 metres at 0.15% (1,539ppm) pU3O8 from 74.51 metres (GT 2,964)
• In-fill drilling in the Inferred Resource envelope of both Blackbush East and Blackbush West to
continue to increase the confidence in Mineral Resource Estimate through conversion of the Inferred
category to Indicated status. Holes have targeted interpreted roll fronts within the mineralised system
with significant uranium intercepts identifying mineralised areas not previously recognised and remain
open for testing by extensional drilling (Figure 1). Significant grade intercepts in the in-fill program
(additional to the above) include:
Blackbush East
o
1.48 metres at 0.13% (1,336ppm) pU3O8 from 61.70 metres (GT 1,977)
Blackbush West
o
1.18 metres at 0.25% (2,557ppm) pU3O8 from 69.68 metres (GT 3,017)
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 4 of 22
The results above combined with drill results to be obtained in the following quarter will be integrated into an
update of the Blackbush Mineral Resource Estimate planned for later this year, targeting an increased
Indicated and Total resource. The results of the resource update will enable evaluation to enhance the recently
announced scoping study (ASX: 14 March 2023).
The Department for Energy and Mining (DEM) are currently assessing an application for ongoing resource
drilling and exploration which will allow continuous drilling activities going forward.
Field Recovery Trial
The Retention Lease (RL) application to enable the operation of the ISR Field Recovery Trial (FRT) is currently
under assessment by State Government agencies and is anticipated to be released in the forthcoming quarter
for public consultation and feedback. AGE will then formulate responses to feedback submissions and update
the RL application for further assessment/approval. A Program for Environmental Protection and Rehabilitation
(PEPR) is required to commence FRT plant and wellfield operations which is currently being drafted. The
PEPR will be submitted post consent of the RL for approval by State Government regulatory agencies.
A full time experienced ISR Process Chemist commenced with AGE, plus ammjohn Pty Ltd (an experienced
Project Engineering and Management group) were engaged late June. Finalisation of the process chemistry,
wellfield and plant engineering designs (in conjunction with Adelaide Control Engineering) is nearing
completion with ordering of containers, control system, reverse osmosis plant, and wellhouse components
(Figure 1 & 2) and other longer lead items well advanced. A total of $615,000 has been committed to date
which includes the required resin for the IX plant.
Figure 1: Side-opening container which will house the FRT ion exchange plant.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 5 of 22
Figure 2: Floor bunding being installed in the FRT wellhouse container.
Due to higher than usual winter rains, delays have been incurred in drilling FRT monitor wells to obtain a
sustained timeline of baseline groundwater quality data which will impact approval timeframes. Whilst the plant
infrastructure and control system are being constructed offsite by GJC Engineers Pty Ltd, Alligator anticipates
a longer schedule for the FRT, with onsite placement of the pilot plant now anticipated during Q1 2024 (subject
to regulatory approval), and operation of the FRT into Q1/Q2 of 2024. This is not anticipated to impact
Alligator’s overall development schedule for Samphire (as outlined in our Scoping Study release – ASX: 14
March 2023) as the planned Feasibility Study for the project is due to commence during Q2 2024.
Big Lake Uranium (BLU) Project
Three significant project milestones were reached this quarter for the execution of the 2023 exploration
program:
1.
2.
3.
The Native Title Agreement for Mineral Exploration with the Yandruwandha Yawarrawarrka Traditional
Landowner Aboriginal Corporation (YYTLOAC) was executed on 6 May 2023. In close consultation with
the traditional landowners, the agreement allows for non-disturbing exploration through to drilling
operations over most of exploration licenses 6367, 6847, 6849, 6902, 6903 and 6904 (Figure 3).
The exploration PEPR for the 2023 field exploration program was submitted in June. The program
covering core tenement EL 6367 proposes a series of drill ‘fences’ to better understand the target
stratigraphy in key areas across the Basin. In total, 5,600 m of air-core drilling is planned over 40 – 45
holes, with average depths of 140 m. Holes will be assayed to further assist with fine-tuning the seismic
interpretation and data integration.
A regional seismic interpretation across the eastern half of EL 6367 was completed during the quarter
which identified several broad, sinuous palaeochannel systems in both the Eyre and Namba formations.
This work is currently guiding target generation for the upcoming drill program.
Post quarter end an initial cultural heritage site visit was undertaken. This will allow detailed siting of drill holes
ready for full clearance for drilling.
Subject to timing of ePEPR approval, weather and final site clearances, drilling is planned for Q4.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 6 of 22
Figure 3: The location for the proposed Exploration Areas under the YY Agreement.
Alligator Rivers Uranium Province (ARUP) – Nabarlek North Project
Following integration of recent geochemical assay results in conjunction with Falcon gravity data (acquired in
2022[1] by AGE), magnetics and other geological datasets, approximately 23 target zones have been
identified for follow-up during the 2023 field program at Nabarlek North (NN). This program includes
reconnaissance IP across up to 20km2 with potential follow-up detailed IP over the best identified
geophysical targets. Drilling will continue geochemical and geological basement investigations across the
approved work area with up to 1800 aircore/reverse air blast drill-holes to complement 2022 work or where
previous drilling programs failed to adequately sample basement. A camp and logistical support have been
established for up to 20 people subsequent to the quarter’s end, with minor delay encountered as a result of
late rains and delayed road openings across the top end. Drilling contractors have now arrived onsite.
Further to 2023 field planning, some additional studies have been conducted during the quarter, including:
-
Reprocessing and filtering of the Falcon gravity gradiometry data to try and enhance structures and
better image low-angle features (considered fundamental to the target concept).
-
Ultra-fines sampling of two hundred assays from samples collected in 2022. The technique was
developed between CSIRO and industry (https://research.csiro.au/ultrafine/ultrafine-next-gen/) and can
provide better detectability of basement-leached elements through cover. Depending on results
(pending, as of 30 June) it will be applied to 2023 assays for uranium exploration as well as testing the
rare-earth potential under cover within the Nabarlek project area.
[1] AGE ASX Release “Quarterly Report for period ending 30 June 2022” 02547148.pdf (weblink.com.au)
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 7 of 22
Piedmont Nickel Cobalt Project - NW Italy.
During the quarter, Alligator completed a reconnaissance field trip to the company’s Piedmont project. In
conjunction with AGE’s local geological specialists, site mapping and sampling was conducted across EM
conductors identified in 2022 at La Balma and Alpe Laghetto (Figure 4). A total of 81 samples were collected
for geochemical analysis, 33 of which have also been submitted for petrophysical analysis and several samples
to follow for petrology analysis.
The field visit was also used to identify potential drilling access and logistical issues, should the geochemistry
results and petrophysics provide compelling evidence for untested, mineralised targets below surface. Results
are expected to be received by the end of July at which time, refined modelling of the EM conductors will be
undertaken.
During the visit, community engagement was overall very positive for renewed activity and exploration interest
in the region. The Company has agreed to an extension of the buyout agreement with CRP until mid-August
2023 in exchange for sole funding the recent field works and incorporating this newly acquired data in the
assessment of prospectivity.
Figure 4: Completed EM survey grids showing Channel 25 conductivity plots and
historic nickel – cobalt working locations.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 8 of 22
Market Update
The spot uranium price improved from US$50 per lb at the March quarter end to over US$55 per lb for the
quarter under review, and at time of writing is at US$56.15 per lb.
AGE attended the WNFM Conference in Europe with our marketing agent Traxys. Meetings were held with
many European and North American nuclear utilities who attended, some of these now the third time Alligator
has met with certain utilities. As advised in previous ASX updates, AGE / Traxys have identified a few potential
anchor utilities who are willing to negotiate early-stage conditional offtake contracts for a portion of future sales.
We would see these discussions advancing as we progress our Field Recovery Trial and commence a
Feasibility Study for Samphire during 2024.
At the WNFM conference, key uranium producers and near producers stated publicly that they are only willing
to increase production further on the basis of firm long-term supply contracts at higher level pricing that will
support the required returns and increased capital costs of that production. Coming on top of the previously
identified shortage of enrichment and conversion services, the pressure on increased nuclear fuel prices is
becoming obvious.
Bell Potter released updated comments on the uranium market on 29 June, summarising their forward
expectations, writing:
“As of March 2023, 57 reactors were under construction around the globe, with 22 of those being in
China. During 2022, 6 new Reactors were connected to the grid at an average capacity of 1,131MWe
(total capacity 9,054MWe) and 5 old reactors were shut down (total capacity 3,271MWe). Thus far in
2023, 4 new reactors have been connected to the grid in Slovakia, China, USA and Belarus (total
capacity 3,772MWe) and 5 old reactors have been shut down in Taiwan, Belgium and Germany (total
capacity 6,048MWe).”
“We continue to see reactor growth across the globe, with China and India boasting both a
comparatively young fleet and ambitious growth outlooks for nuclear capacity. We estimate current
raw U3O8 demand at 161Mlbs/yr, expanding to 189Mlbs/yr by the end of the decade. We currently
estimate global supply for U3O8 at ~125Mlbs/yr, expanding by ~11.48Mlbs over 2023 with the addition
of restart operations, namely McArthur River. As it stands, we currently estimate a ~24Mlbs shortfall
in the market in 2023”
In their regular U Weekly release, Cormark Securities Inc. made the following significant updates around SMR
news:
“Small Modular Reactors (SMR) remain in the headlines with an MOU signed with NuScale in
Romania, collaboration between France and Belgium on EDF’s NUWARD SMR design, a Rolls
Royce/Sumitomo study showing the potential for a 470 Mwe SMR design to support the UK’s hydrogen
network and Slovakia’s utility signing agreement in support of SMR development amongst other news
on this front.”
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 9 of 22
Spot uranium price chart for 12 months to 26 July 23
Source – Trading Economics
Corporate
During the quarter the Company announced significant progress had been made over the first two years of the
strategic relationship formed in May 2021 with Traxys North America LLC (Traxys), the U.S. arm of the global
commodities trading group Traxys. Under the agreement announced on 10 May 2021, Traxys is providing
uranium marketing services for future uranium production long-term offtake contracting, will consider potential
support in project development financing and is assisting in uranium and energy minerals project acquisition
opportunities. The benefits being derived from this relationship, include:
•
•
•
•
•
Co-ordination of over 25 meetings in the last two years with nuclear utilities based both in the US and
Europe;
Identification of several key anchor nuclear utilities willing to discuss establishment of conditional
offtake contracts with Alligator around the time of progression of a feasibility study for the Samphire
Project which is currently targeted for 2024;
Joint attendance at several global nuclear conferences, including the recent World Nuclear Fuel
Market meeting where uranium and nuclear fuel component upwards price pressure was a significant
point of discussion;
Continued involvement in the evaluation of external uranium resource opportunities to develop a future
supply pipeline; and
Provision of regular uranium and nuclear market updates to both the Board and Management.
On 30 June 2023, Bell Potter initiated research coverage on Alligator with the release of their initial research
report. Shareholders and investors can access this research report on AGE’s website in the Investor –
Research area, or through the following link: Research – Alligator Energy
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 10 of 22
Capital Structure and Listing Rule 5 disclosures.
At 30 June 2023, the Company had the following capital structure and cash balances:
As at 30 June 2023
Cash Balance
A$18.5M
Ordinary Fully Paid Ordinary Shares (AGE)
3,306.0M
Unlisted Options 8.1c (Exp 01/12/25)
132.0M
Unlisted Employee Incentive Performance Options
14.3M
Big Lake Performance Shares (see Appendix 1)
30.0M
During the quarter 3,501,202 zero strike priced options were granted to the COO for the FY23/24 performance
period on the basis of 50% of these representing a short-term incentive assessed over a twelve-month period
against pre-determined KPIs and 50% linked to long-term hurdles associated with driving shareholder value.
Expenditure on exploration and evaluation activities during the June quarter totalled $2,079k (previous quarter
- $1,145k) and related principally to advancing the Samphire, Nabarlek North and Piedmont Projects.
Payments to related parties including non-executive director fees and the salary of the CEO and Managing
Director for the March quarter totalled $122k (previous quarter $122k).
This announcement has been authorised for release by the Board.
Contacts:
For more information, please contact:
Mr. Greg Hall
Mr. Mike Meintjes
CEO & Director
CFO & Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 11 of 22
Competent Person’s Statement
Uranium Exploration
Information in this report is based on current and historic Exploration and Resource Drilling Results compiled by Dr Andrea
Marsland-Smith who is a Member of the AusIMM. Dr Marsland-Smith is employed on a full-time basis with Alligator Energy
as Chief Operating Officer, and has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration (including 21 years in ISR uranium mining operations and technical work) and to the activity she is
undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves. Dr Marsland-Smith consents to the inclusion in this release of
the matters based on her information in the form and context in which it appears.
Nickel Cobalt
Information in this report is based on current and historic Exploration Results compiled by Mr Geoffrey Chapman who is a
Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr Chapman is a Consultant Geologist with Alligator
Energy Limited and has sufficient experience which is relevant to the style of mineralisation and type of deposit under
consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Chapman consents to
the inclusion in this release of the matters based on his information in the form and context in which it appears.
Forward Looking Statement
This report contains projections and forward looking information that involve various risks and uncertainties regarding future
events. Such forward-looking information can include without limitation statements based on current expectations involving
a number of risks and uncertainties and are not guarantees of future performance of the Company. These risks and
uncertainties could cause actual results and the Company’s plans and objectives to differ materially from those expressed
in the forward-looking information. Actual results and future events could differ materially from anticipated in such
information. These and all subsequent written and oral forward-looking information are based on estimates and opinions
of management on the dates they are made and expressly qualified in their entirety by this notice. The Company assumes
no obligation to update forward-looking information should circumstances or management’s estimates or opinions change.
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 12 of 22
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration, development and operations
of both uranium and nickel projects (both laterites and sulphides).
Projects
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 13 of 22
Alligator Group Tenure holdings at Quarter End:
ARUP (NT) Uranium
EL24921
Tin Camp Creek
TCC Project P/L
98
76.79
NT
Granted
EL24922
Tin Camp Creek
TCC Project P/L
98
194.59
NT
Granted
EL25002
Tin Camp Creek
TCC Project P/L
100
11.55
NT
Granted
EL24291
Beatrice
Alligator Energy Ltd
100
337.21
NT
Granted
EL26796
Beatrice
Alligator Energy Ltd
100
19.77
NT
Granted
EL27252
Stevens
Northern Prospector P/L
100
6.75
NT
Granted
EL27253
Stevens
Northern Prospector P/L
100
5.61
NT
Granted
EL28389
Nabarlek North
Northern Prospector P/L
100
110.83
NT
Granted
EL28390
Nabarlek North
Northern Prospector P/L
100
33.58
NT
Granted
EL29991
Nabarlek North
Northern Prospector P/L
100
26.87
NT
Granted
EL29992
Nabarle
Share your feedback
Discover