Alligator Energy – Annual General Meeting 2024
Disclaimer
Forward Looking Statements
This presentation contains projections and forward-looking information that involve various risks and uncertainties regarding future events. Such forward-looking information can
include without limitation statements based on current expectations involving a number of risks and uncertainties and are not guarantees of future performance of the Company.
These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ materially from those expressed in the forward-looking information. Actual
results and future events could differ materially from anticipated in such information. These and all subsequent written and oral forward-looking information are based on estimates
and opinions of management on the dates they are made and expressly qualified in their entirety by this notice. The Company assumes no obligation to update forward-looking
information should circumstances or management’s estimates or opinions change.
Competent Person’s Statement – Uranium and Previously Reported Information
Information in this report is based on current and historic Exploration and Resource Drilling Results compiled by Dr Andrea Marsland-Smith, who is a Member of the AusIMM. Dr
Marsland-Smith is employed by Alligator Energy as Chief Operating Officer (COO) and has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity she is undertaking (including 15 years working with ISR uranium development and operations) to qualify as a Competent Person as defined in
the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr Marsland-Smith consents to the inclusion in this release of
the matters based on her information in the form and context in which it appears.
In relation to Exploration results and Mineral Resource estimates referred to in the announcements referred to on slides 5,7,8,9,10,11,12 and 17 the Company confirms that it is not
aware of any new information or data that materially affects the information included in the original market announcement and that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. In relation to production target referred to on slides 10 and 12,
the Company confirms that all material assumptions underpinning the production target, and the forecast financial information derived from the production target, in the initial
announcement continue to apply and have not materially changed.
Competent Person’s Statement – Nickel Cobalt exploration
Information in this report is based on current and historic Exploration Results compiled by Mr Geoffrey Chapman who is a Fellow of the Australasian Institute of Mining and
Metallurgy. Mr Chapman is a Consultant Geologist with Alligator Energy Limited and has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves. Mr Chapman consents to the inclusion in this release of the matters based on his information in the form and context in which it
appears.
2
Alligator Corporate Presentation | November 2024 | ASX:AGE
ESG in practice: Operating philosophy
• We aim to add value in all of our decision-making for
shareholders.
Shareholders
• We wish to provide an engaging, challenging, enjoyable and
respectful workplace for our employees.
• We respect the rights of landowners and communities and
Team
Communities
seek to collaborate for our mutual benefit.
Stakeholder
Perspective
• We respect the cultural heritage and connection to country of
Traditional Owners and wish to create mutually beneficial
opportunities.
Focus on
Environment
Landowners
• We aim for a low impact on the environment, through
innovation, use of latest technology, and responsible land
management techniques.
Traditional
Owners
Our aim is to discover, source and economically extract these needed commodities with an innovative approach,
with either zero or minimal impact, and with positive value and experience for our stakeholders and communities.
3
Alligator Corporate Presentation | November 2024 | ASX:AGE
Uranium and Nuclear Fuel market
• Primary mine supply, mine re-starts, new mines under development
plus new planned mines still potentially not adequate for future supply.
• Re-start and new mines are experiencing delays due to approvals,
typical / usual ramp up and commissioning issues, and lack of
experienced development / design skills.
• Geopolitics impacting supply – US restrictions on Russian imports, and
now Russia banning EUP sales to the US.
• Reliable nuclear power for AI driven data-centre expansion being
targeted and supported
• Utilities now coming out for long-term U3O8 supply requests from 2028
onwards.
• Existing producers will find ways to extend mine life, however will also
take time.
• Russian EUP exported into China, with China EUP sales to the US now
under review.
• Faster to build a nuclear plant in China and India than it is to start a
uranium mine in Australia.
4
Alligator Corporate Presentation | November 2024 | ASX:AGE
2024 Highlights and achievements
• Dec 2023 – Samphire Resource update to 17.5 Mlbs with 75% indicated resource – Exploration target range
• Dec 2023 – Samphire Scoping Study update to 1.2Mlbs pa production
• Jan 2024 – Investment into EnviroCopper – copper ISR development company
• Mar 2024 – Samphire Retention Lease formal response to submissions document lodged with DEM
• May 2024 – Extensions to Samphire palaeochannel system by 50% from ground gravity survey
• May 2024 – Initial release of 2024 Samphire resource drilling results
• May 2024 – Inaugural aircore drilling program commences on Big Lake Uranium project
• June 2024 – Fabrication of Samphire pilot plant for field trial complete and delivered to AGE Whyalla yard
• Jul 2024 – High resolution airborne magnetic and radiometric survey completed over Nabarlek North
• Jul 2024 – Final Samphire Retention Lease response document submitted to the DEM post RFI’s
• Aug 2024 – Targeted RC drilling program commences over Nabarlek North with 3,500m over 8 target areas
• Aug 2024 – Significant new uranium discovery at Big Lake project with U mineralisation in palaeochannel sands
• Oct 2024 – Assay results validate significant uranium discovery at Big Lake – Cultural clearance for 2025 drilling
5
Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Uranium project: South Australia – experience in uranium
6
Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Highlights
20kms from
Whyalla, SA
JORC compliant
resource
Regional exploration
opportunities
Excellent regional
infrastructure and
skilled labour-force
17.5 Mlbs uranium resource
with significant scope for
further growth
Exploration Target
estimates additional
14 - 75 Mlbs
Note: the potential quantity and grade of the Exploration Target is
conceptual in nature as there has been insufficient exploration to date to
estimate a Mineral Resource and it remains uncertain whether further
exploration will result in the estimation of a Mineral Resource
Robust Scoping Study1.2 Mlb / annum prod.
Pilot plant
planned
A$131m capex, 42% IRR,
and 2.45 yr payback
Fabricated and delivered to
site. Construction in Q4
subject to approvals
Refer ASX release 14 December 2023
“Scoping Study Update”
7
Alligator Corporate Presentation | November 2024 | ASX:AGE
ESG
Strong ESG credentials,
with environmental
commendation awarded by
SA government
Samphire Uranium project: A highly competitive In-Situ Recovery project
• Initial capital cost estimate of A$131 million is low,
despite significant contingencies and inflation totalling
35%.
• AISC at the lower end of cost curve, due to:
➢ In-situ Recovery (ISR) amenable,
➢ nature of the deposit, shallow depth, excellent
formation porosity, and
➢ high leaching dynamics.
• Location near Whyalla affords lower cost of key
infrastructure, locally based workforce (i.e. no FIFO or
camp), experienced mining services and business support.
• Expansion potential - Exploration Target Range (Dec 23)
estimating an additional 14 - 75 Mlbs on top of 17.5Mlbs
resource. Multi-year resource extension and step-out
drilling to increase mine life and production rate.
• Field Recovery Trial on receipt of regulatory approvals
(approx. Q4), to de-risk project and confirm parameters to
be used in a full feasibility study during 2025
8
Alligator Corporate Presentation | November 2024 | ASX:AGE
Conceptual Model of ISR
Samphire Uranium Project – Dec 2023 Scoping Study† : 1.2 Mlbs pa project
Study metrics* at US$75 / lb uranium price
A$131m
2.45 years
42%
A$257m
US$33.31/lb
US$16.06/lb
CAPEX
Payback
IRR*
NPV8*
AISC
Cash Costs
(post-tax, real,
ungeared)
(post-tax, real,
ungeared)
(A$47.58/lb)
(A$22.94 /lb)
(including contingency)
Study metrics* based on analysts current long-term price projections of US$90 / lb
A$131m
1.93 years
55%
A$371m
US$34.06/lb
US$16.06/lb
CAPEX
Payback
IRR*
NPV8*
AISC
Cash Costs
(post-tax, real,
ungeared)
(post-tax, real,
ungeared)
(A$48.96/lb)
(A$22.94/lb)
(including contingency)
† Ref ASX release 14 December 2023 “Scoping Study Update”: Alligator confirms that all material assumptions underpinning the ‘production target’ or the forecast financial information derived from the
‘production target’ continue to apply and have not materially changed other than the outlook for the long-term uranium price as set out above; *Calculated using 0.70 US/A$ exchange rate inclusion of significant
contingencies and inflation of 35%.
9
Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Uranium Project – Blackbush Dec 2023 JORC Resource
JORC
Category
Mt
Grade
(U3O8 ppm)
U3O8 Metal
(KTonnes)
U3O8 Metal
(Mlbs)
Indicated
7.8
754
5.9
12.9
Inferred
4.6
447
2.1
4.6
Total
12.4
640
7.9
17.5
Ref: ASX Release 7 December 2023
10 Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Uranium Project – Blackbush 2024 Drilling
Significant uranium mineralisation intersections from Blackbush West uranium
roll fronts has delivered further targets outside of the Inferred mineral resource.
Announced in ASX release dated 21 Nov 2024:
•
•
•
•
•
•
•
•
•
BBRM24-304: 1.3 meters at 1.94% (19,391ppm) pU3O8 from 62.6m (GT 25,208)
BBRM24-278: 1.1 meters at 0.44% (4,392ppm) pU3O8 from 62.94m (GT 4,832)
BBRM24-338: 2.4 meters at 0.20% (1,948ppm) pU3O8 from 56.7m (GT 4,675)
BBRM24-321: 1.1 meters at 0.36% (3,633ppm) pU3O8 from 58.59m (GT 3,996)
BBRM24-282: 1.7 meters at 0.23% (2,314ppm) pU3O8 from 63.1m (GT 3,934)
BBRM24-283: 0.8 meters at 0.45% (4,506ppm) pU3O8 from 65.03m (GT 3,604)
BBRM24-318: 0.7 meters at 0.36% (3,566ppm) pU3O8 from 59.1m (GT 2,497)
BBRM24-330: 0.8 meters at 0.18% (1,791ppm) pU3O8 from 63.1m (GT 1,433)
BBRM24-314: 0.6 meters at 0.17% (1,734ppm) pU3O8 from 59.14m (GT 1,040)
An update of the JORC Resource Estimate, inclusive of the January to mid-April
drill results to be completed in Q1, 2025, targeting both resource expansion and
category conversion from inferred to indicated
Note: pU3O8 denotes that the grade has been determined by Prompt Fission Neutron
downhole logging
GT= grade(ppm) x thickness(m) – divide by 10,000 for m% GT
ASX release 1 May 2024 – Extension of Uranium Mineralisation at Samphire, and ASX
release 21 Nov 2024 – Significant Drilling Results – Samphire Uranium Project Update
11 Alligator Corporate Presentation | November 2024 | ASX:AGE
Further Extensions outside the Exploration Target Range Envelope
Ground Gravity Survey- April 2024
•
Exploration target range – additional 14 to 75 Mlbs
•
Ground gravity data shows outstanding continuity of the
Samphire palaeochannel system by 34 lineal km’s.
•
50% increase to the existing palaeochannel strike length to
~over 90kms.
•
Historical drillholes confirm that extensions contain the same
thick sequences of Kanaka Bed sands which host the
Blackbush Mineral Resource .
•
Multiple historical drillhole intersections (above 250ppm
eU3O8 cutoff) confirm that uranium is ubiquitous throughout
this system.
•
72% (over 70km) of the prospective areas of the entire
Samphire palaeochannel system remain completely untested
by drilling.
•
Significant potential for new discoveries and resource growth
in the Project area.
Refer ASX Announcements 7 December 2023 and 2 May 2024
12 Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Uranium Project – Field Recovery Trial (FRT)
• Field Recovery Trial (FRT) construction targeted for end Q1
2025, pending regulatory approvals. Plant fully fabricated and
delivered to AGE’s Whyalla yard.
• Post construction – FRT in operation for 3-4 months and consists
of three producing well patterns and a containerised pilot plant.
• FRT is designed to confirm key operating parameters and marks
an important step toward development.
• Parameters to be assessed include in-situ chemistry,
hydrogeology, uranium recovery, reagent usage, and other
environmental and economic factors.
• Data and learnings further de-risk the Project and provides the
necessary inputs to a full feasibility study and Mining Lease
Application during 2025.
Wellhouse (Pipe room) Module
13 Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Uranium Project – Field Recovery Trial Plant
• Fabrication of the containerised FRT processing
Pilot plant layout
plant completed - delivered to AGE’s Whyalla
yard in June 2024.
• Expressions of Interest to five Whyalla based
companies for onsite civils and pilot plant
construction evaluated. Preferred company to
be announced in coming weeks.
• Plant control system being set up and tested.
Commissioning and operating plans under
development for initiation.
• Post-FRT and subject to any further testing, well
infrastructure and plant to be removed, and area
rehabilitated – pilot plant available for future
satellite field testing.
• Samples of final clean eluate solution containing
extracted uranium oxide to be further processed
into U3O8 concentrate offsite for Converter
quality samples.
14 Alligator Corporate Presentation | November 2024 | ASX:AGE
Ion Exchange Module
Wellhouse Module (pipe room)
Delivered to site
Exploration projects
NT, AUSTRALIA
ITALY
Piedmont NW
Alligator Rivers
(ARUP)
High Grade U
Ni-Co-Cu-Au-PGEs
SA, AUSTRALIA
Big Lake
(Cooper Basin)
ISR style U
SA, AUSTRALIA
Investment in
EnviroCopper Ltd
Copper ISR
15 Alligator Corporate Presentation | November 2024 | ASX:AGE
Big Lake Uranium Project, SA
•
Overlies Cooper Basin in NW SA – under-explored for
uranium despite geological analogies to world-class ISR
fields in hydrocarbon basins - Kazakhstan, Wyoming, Texas.
•
Several potential uranium sources including; weathering /
leaching of underlying ‘hot’ granite suite or distal migration of
uranium bearing fluids toward basin depo-centres.
•
EM results and analysis of publicly available 2D seismic data
indicated potential presence of paleochannel systems.
2024 Big Lake Drilling Program:
•
Interpretation of seismic and other datasets towards a full 3D
basin model across the entire basin.
•
Selection of ~20 drill sites to test stratigraphy, paleochannel
model and qualities of U-trap rocks
•
•
•
Traditional Owner clearances for drill lines.
Engagement with other key stakeholders
Remote logistics considerations, including access to fuel,
water, accommodation and emergency support
Alligator Corporate Presentation | November 2024 | ASX:AGE
Big Lake Uranium - Inaugural Drilling Program Discovery Success
• Inaugural drilling program intersected significant thicknesses of
anomalous uranium mineralisation within interbedded
palaeochannel sand units in the Namba Formation.
• Discovery is first proof of concept that significant uranium is present
within Lake Eyre basin sediments above the hydrocarbon-rich
Cooper Basin within potentially ISR amenable host and depths.
• Laboratory chemical assay results validate the in-field XRF
measurements for contained uranium. These include:
• AC24-021
• AC24-022
• AC24-023
• AC24-025
20m @ 110 ppm U from 106 m
35 m @ 117 ppm U from 93 m
5 m @ 47 ppm U from 104 m
10 m @ 138 ppm U from 108 m
• The indicative grade-thickness of two intersections is at or near the
economic cut off used at the Company’s Samphire ISR uranium
project near Whyalla, SA.
• Cultural heritage clearance complete for expanded drilling program
in early 2025 – to include rotary mud drilling allowing detailed downhole logging.
Alligator Corporate Presentation | November 2024 | ASX:AGE
Refer ASX releases 13 August 2024 and 23 October 2024
Alligator Rivers Uranium Province, NT
• Three projects: Nabarlek North, Tin Camp Creek and
Beatrice, in Australia’s premier high-grade uranium
province.
• Province is host to existing high-grade deposits including
Jabiluka (358Mlb @ 5,300ppm U3O8).
• Multiple uranium targets in well-defined regional uranium
bearing zone including the Caramal Resource 6.5 Mlbs
U3O8 @3,100ppm.
• Nabarlek North is the current focus of exploration
program – including northerly extensions to the U40
Prospect*, based on 2023 results (AGE and 3rd party).
• A small field program will be carried out on the Tin Camp
Creek project in 2024 to revisit preferred targets for
future work.
* Includes 6.3m at 7.23% U3O8 and 8.3m @ 2.12% Cu (Uranium Equities Ltd now DevEx
Resources Ltd release – 4 October 2017).
Alligator Corporate Presentation | November 2024 | ASX:AGE
Alligator Rivers Uranium Province, NT
2024 Work Program at Nabarlek North:
• New high resolution airborne magnetic / radiometric
Focus drilling areas, 2024
survey to better define key structures and host
stratigraphy across the entire tenure (completed July
2024)
• Reconnaissance mapping of outcrop throughout northern
half to ‘truth’ regional stratigraphic knowledge and tie
geophysical data.
• An RC drilling program of ~ 3,500m focussed on 8 target
areas across the tenement (completed Sept 2024).
• Includes further work at U40 North – to follow up last
year’s intercept and ‘chase’ system to the north.
• Awaiting assays on samples collected
• Drilling / geophysics programs co-funded with NT Govt as
part of their 2024 ‘Resourcing the Territory’ Program
Alligator Corporate Presentation | November 2024 | ASX:AGE
U40 Prospect
Investment into EnviroCopper Ltd ISR copper, SA
• Alligator expanded energy minerals interests with $0.9M strategic
investment in private group, EnviroCopper (ECL).
• This investment and resultant collaboration is extremely
complimentary to our existing and substantial in-house ISR expertise.
• Provides exposure to ISR copper project portfolio (over 200kt Cu
resource) and experienced ISR and research team.
• Advancing ISR trials at Kapunda copper project - similar plans for
Alford West copper project. BHP funding field trials at Kapunda for IP
access.
• ISR successfully used to extract copper in projects in Australia and the
US - offers distinct advantages and environmental benefits.
• ECL has now undertaken successful push-pull lixiviant trial at
Kapunda to extract copper – awaiting approval for SELT trial within
ring of holes circulating lixiviant for copper extraction.
• Significant in-house Cu ISR modelling expertise for shallow fractured
rock aquifer hosted oxide copper deposits.
20 Alligator Corporate Presentation | November 2024 |
ASX:AGE
2025 Key aims, targets and tasks
• Estimated Dec 2023 – Samphire Retention Lease approval (subject to final Ministerial decision) – information
finalised in July 2024, we understand internal documentation and final administrative matters underway.
• Estimated Feb 2025 – Submission of Field Recovery Trial (FRT) – Program for Environmental Protection and
Rehabilitation (PEPR) for the FRT operations
• Q1 2025 – Samphire Blackbush deposit updated JORC resource – input from 2024 extensional and infill drilling, plus
detailed re-logging of historical holes for more accurate host lithology.
• Feb 2025 – Re-start of Blackbush extensional drilling
• Early Mar 2025 – Big Lake second drilling program start up
• Apr / May 2025 – FRT construction followed by operations
• 1H 2025 – Discussion and negotiation of pastoral access arrangements for drilling southern extension of Blackbush,
and infill drilling of Plumbush prospect.
• 1H 2025 – EOI and selection for Feasibility Study management – 2H Feasibility Study execution
• Q1 2025 – Alligator Rivers data review and workshop on next steps and targets – 2025 exploration plan
• 2H 2025 – Heritage clearance and third drilling program for Big Lake project
• 2H 2025 – Document development and finalisation of Mining Lease application for Samphire project
21 Alligator Corporate Presentation | November 2024 | ASX:AGE
ASX:AGE
Greg Hall CEO
+61 (0) 7 3839 3904
gh@alligatorenergy.com.au
www.alligatorenergy.com.au
Board & Management
Paul Dickson | Non-Executive Chairman
Paul is a finance and corporate advisory professional with more than 30 years’ experience
in the finance services industry. He was a Founding Director at Paradigm Capital, a
boutique corporate advisory firm specialising in junior and mid-tier ASX listed resources
companies, and a Director of Proserpine Capital a private equity firm for circa 4 years.
Paul has been an AGE Board member since inception and Chairman for 3 years.
Callum McIntyre | Alternate Director
Callum has extensive experience in the finance and technology industries, both in
Australia and overseas. He is currently Director Business and Investment at Labonne
Enterprises, a private investment company. He is also Business Operations Manager at
Macallum New Energy, a private Company focused on the exploration and production of
gas in the Perth Basin. He holds a BSc from the University of WA, a Graduate Diploma
of Applied Finance, and is a Graduate Member of the Australian Institute of Company
Directors (GAICD).
Gregory Hall | CEO & Managing Director
Mike Meintjes | CFO & Company Secretary
Greg is an experienced mining engineer and CEO with 35+ years’ experience in
uranium and other mine management. He previously held roles at WMC Olympic
Dam & nickel mines, LKAB Iron Ore (Sweden), ERA Ranger & Jabiluka Uranium and
international commodities marketing with Rio Tinto (ERA) Uranium, and Bauxite &
Alumina groups. Greg was also founding CEO of Toro Energy Ltd.
Chartered Accountant/CFO/Company Secretary. Over 30 years professional
services principally with a Big Four accounting firm and recently in part-time
contracting and consulting roles. Extensive exposure to mining, oil & gas sectors in
WA, QLD and South Africa. CFO and Co Sec for AGE for 11 years
Peter McIntyre | Non-Executive Director
Dr Andrea Marsland-Smith | COO
Peter is a civil engineer and experienced CEO. He previously held GM roles with
WMC Ltd, including development of major mining projects. Peter was the founding
MD of Extract Resources during the discovery and pre-feasibility of Husab Uranium
mine in Namibia, sold for US$2.2 billion.
Andrea was previously at Heathgate Resources with roles over 15 years covering
technical and field positions in Geology, Head of Geology, Head of Regulatory &
Compliance, Head of Operations and Head of Government Relations and
Indigenous Affairs. She holds a PhD in Economic Geology and was the recipient of
Exceptional Women in Resources in 2016.
Fiona Nicholls | Non-Executive Director
Fiona has 30 years of experience working across a range of business functions
including strategy, planning, ESG and operations, multi-country project
development and approvals and due diligence processes. Fiona was previously on
the Board of Rössing Uranium and alternate director for ERA uranium.
23 Alligator Corporate Presentation | November 2024 | ASX:AGE
Management and operating team with extensive uranium mine
operations experience, particularly with In-Situ Recovery (ISR),
including stakeholder engagement, approvals, operations, uranium
marketing and contracting, environmental and sustainable
production.
Greg Hall (CEO), Andrea Marsland-Smith (COO), Paul Dickson
Company Snapshot
(Chair), Fiona Nicholls (NED)
Capital Structure (as at 24 Oct 2024)
Share Price
$0.048
Ordinary Shares
3,869.8 M
Perf Shares, Listed & Unlisted Options
461.6 M
Cash as at 30 June 2024
$ 28.7 M
Market Cap
$186 M
Top 50 Shareholders
Brokers &
Banks
19%
Retail
45%
Directors
&
Executives
5%
Institutions
31%
24 Alligator Corporate Presentation | November 2024 | ASX:AGE
Samphire Uranium Project: Opportunity for a near carbon-free energy project
• Lower power consumption as ISR method has no rock /
material movement, nor crushing / grinding of rock.
Renewable power with backup may be adequate?
• Distance to Whyalla may allow all electric vehicles, light
trucks, cranes etc to be used?
• Advances in battery on-highway prime movers may support
the level of logistics and product transport needed?
• This potential opportunity aligns with SA Government
Hydrogen Hub for Whyalla region and extensive potential
renewable projects.
• We will be scoping this opportunity in parallel with our
feasibility and economic studies.
25 Alligator Corporate Presentation | November 2024 |
ASX:AGE