Quarterly Report and Appendix 5B for 30 September 2025
Released
Released
Announcement PDF
QUARTERLY REPORT
FOR THE PERIOD ENDING
31 December 2021
ASX: AGE
30 September 2025
2
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 2 of 14
Transformational quarter as Alligator commences Samphire construction and
strengthens team for next growth phase
Highlights for the Quarter:
• Final approval received to commence construction of the Samphire Field Recovery Trial.
• Construction and drilling activities well advanced, with site works progressing ahead of schedule.
• Strengthened executive team to drive the Company’s next growth phase.
• Strong momentum across the portfolio, setting up a steady pipeline of newsflow in the coming quarters.
CEO Statement
Commenting on the September 2025 quarter, Alligator Energy’s CEO Andrea Marsland-Smith said:
This has been a pivotal quarter for Alligator Energy, marking the point at which years of detailed
technical work, regulatory engagement and planning have culminated in approval to commence
the Samphire Field Recovery Trial (FRT). With all necessary approvals now secured and
construction well underway, Alligator has moved decisively into the execution phase – the most
significant step yet on our pathway toward development and production.
The commencement of on-ground activities at Samphire represents far more than a construction
milestone; it signifies the transition of Alligator from explorer towards becoming a developer. The
FRT will generate the critical data needed to finalise our feasibility study and supporting mining
lease approvals, This achievement is a testament to the tireless efforts of our technical team,
contractors, and regulators who have worked collaboratively to reach this point.
In parallel, we have strengthened our executive team to ensure we have the capability and
leadership required to deliver on this next phase of growth. The appointment of Joe Sutanto (CFO
& Company Secretary), David Brink (GM Operations) and Christian Knott (GM Approvals &
Sustainability), adds the depth and experience needed to take the Samphire project forward. With
this team in place, and a clear operational focus, Alligator is exceptionally well positioned to
capitalise on the strong uranium market and advance our portfolio of projects with confidence.
The months ahead will be transformative for Alligator Energy as construction at Samphire
progresses toward completion by the end of calendar year 2025 and commissioning begins in
early 2026. With multiple workstreams advancing in parallel, shareholders can expect a strong
pipeline of newsflow and operational milestones over the coming quarters.
I would like to thank our shareholders, employees, and partners for their continued support as we
deliver on our vision to establish Alligator as Australia’s next uranium producer.
3
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 3 of 14
Samphire Uranium Project Development
The Company made significant progress at its Samphire Uranium Project during the quarter, advancing the
FRT towards full construction and commissioning. The FRT represents the critical next step in de-risking
Samphire and validating the in-situ recovery (ISR) parameters that will underpin the upcoming Definitive
Feasibility Study (DFS), mining lease application, and future production planning.
On the back of close engagement with the South Australian Department for Energy and Mining (DEM), final
approval of the Program for Environment Protection and Rehabilitation (PEPR) was secured in August. This
approval marked a major milestone for Alligator, enabling on ground activities to commence. The approval
demonstrates the strength of Alligator’s environmental and technical work programs and the collaborative
relationship developed with government and local stakeholders throughout the assessment process.
With approvals in place, mobilisation of contractors and equipment commenced shortly after quarter end.
Alligator executed a construction contract with lead contractor Ahrens Group to deliver site civil and mechanical
works, including wellfield infrastructure, foundations, pipework, tanks, and site facilities. The drilling contractor,
Watson Drilling, supported by downhole wireline and hydrogeological monitoring teams are working through
delivery of the wellfields and associated monitoring and disposal wells. These early works have laid the
foundation for a safe and efficient rollout of the FRT wellfield.
Construction and drilling activities are well underway, with approximately 75% of the planned production and
recovery wells completed by early October – ahead of schedule. The site has transitioned into full operational
mode, with civil construction, tank installation, and process infrastructure advancing steadily. The Company’s
focus has been on quality execution and maintaining a strong safety and environmental performance record,
supported by ongoing engagement with the Whyalla community and local contractors.
Looking ahead, construction of the Field Recovery Trial is expected to be completed within calendar year 2025,
with commissioning activities scheduled to commence before year end and run into mid January 2026. The
FRT will then operate for several months, with initial recovery data anticipated between February and April
2026. The trial is designed to confirm key ISR parameters including uranium recovery efficiency, solution
chemistry, flow rates, and environmental performance. These data will directly inform the DFS and Mining
Lease application process, both of which are progressing in parallel. The Company’s goal remains to position
Samphire for development readiness, with technical, regulatory, and operational workstreams converging
towards a production decision.
Alligator continues to view Samphire as one of the most advanced ISR uranium projects in Australia and
remains committed to fast-tracking its pathway to development. The current global uranium market strength
reinforces the strategic importance of the Project and the Company’s focus on building a domestic uranium
production base aligned with the clean energy transition.
4
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 4 of 14
Figure 1. Construction commencing on the Field Recovery Trial
Big Lake Uranium Project
Exploration activity at the Big Lake Uranium Project continued to build on the exciting results achieved in late
2024 and early 2025, where drilling intersected significant thicknesses of unconsolidated sands hosting
elevated uranium values. Four holes returned uranium grades exceeding 100 ppm, including two intersections
within porous sand units of more than 20 metres thickness. These results have confirmed the presence of a
highly prospective geological setting within the Namba and Eyre Formations, reinforcing Alligator’s confidence
in the region’s potential to host a large scale ISR amenable uranium system.
Planning is now underway for a revised air core drilling program, expected to commence this financial
year following the recent flooding and heavy rains through the region. Ongoing collection of historic
gamma information from petroleum wells, re-logging and analysis (lithological/gamma) of drill core stored
at the Adelaide Drill Core Library and redox logging of 2024 BLU air core chips were also conducted
across a number of the Big Lake EL’s this quarter.
Other Projects
Alligator Rivers Uranium Province (ARUP)
Work at the Company’s ARUP Projects during the quarter focused on retaining the projects in good standing
through compliance reporting and in-house technical works, along with progressing approvals and targeting
activities for the next phase of exploration activity.
EnviroCopper Limited (15.61% interest)
During the quarter, EnviroCopper continued to advance activities across both the Kapunda and Alford
projects. At Kapunda, groundwater pre-conditioning commenced in preparation for the 90-day in-ground
circulation trial. At Alford, baseline groundwater monitoring is ongoing, and a tracer test was conducted
to assess the physical well connectivity.
5
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 5 of 14
Corporate
During the quarter, Alligator strengthened its leadership team to support the ramp up in activity and drive the
Company through its next phase of growth. Effective 1 July 2025, Dr Andrea Marsland-Smith was appointed
Chief Executive Officer, bringing extensive operational and strategic leadership experience to guide Alligator
towards development – with Greg Hall transitioning to a part-time Executive Director role focused on marketing
and investor relations, ensuring strong continuity in stakeholder engagement and uranium marketing.
Further reinforcing the management structure, Alligator announced the appointment of Joe Sutanto as Chief
Financial Officer and Company Secretary, David Brink as General Manager Operations, and Christian Knott
as General Manager Approvals & Sustainability. These appointments add deep financial, operational, and
ESG capability to the executive team.
During the quarter, the Company:
• Invested $1.0m on exploration and evaluation activities (June 2025 quarter: $2.0m); and
• Paid Executive Director salaries and Non-Executive Director fees of $130,615.
This announcement has been authorised for release by the CEO.
6
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 6 of 14
As at 30 September 2025
Cash Balance A$25.3M
Ordinary Fully Paid Ordinary Shares (AGE) 4,430.1M
Listed Options 7.8c (Exp 28/11/25) (AGEOC) 274.0M
Listed Options 4.7c (Exp 08/09/27) (AGEOD) 278.2M
Unlisted Options 8.1c (Exp 01/12/25) 132.0M
Unlisted Employee Incentive Performance Options 39.9M
Director Share Options 14.4M
Contacts:
For more information, please contact:
Ms Andrea Marsland-Smith Mr Joe Sutanto
CEO CFO & Company Secretary
ams@alligatorenergy.com.au joes@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
Uranium
Information in this report is based on current and historic Exploration and Resource Drilling Results related to the Alligator
projects is based on and fairly represents information provided by Dr Andrea Marsland-Smith who is a Member of the
AusIMM. Dr Marsland-Smith is employed by Alligator Energy as Chief Executive Officer (CEO) and has sufficient
experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity she
is undertaking (including 21 years working with ISR uranium development and operations) to qualify as a Competent
Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves. Dr Marsland-Smith consents to the inclusion in this release of the matters based on her information in
the form and context in which it appears.
In relation to Exploration results referred to in this Quarterly report, the Company confirms that it is not aware of any new
information or data that materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply
and have not materially changed. In relation to the mineral resource estimate referred to in AGE ASX release 6 May 2025
or the production target referred to in AGE ASX release 14 December 2023 that is relevant for underpinning the field
recovery trial at Samphire, the Company confirms that all material assumptions underpinning the production target, and
the forecast financial information derived from the production target, in the initial announcement continue to apply and have
not materially changed.
Competent Person’s Statement
7
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 7 of 14
This announcement contains projections and forward-looking information that involve various risks and uncertainties
regarding future events. Such forward-looking information can include without limitation statements based on current
expectations involving a number of risks and uncertainties and are not guarantees of future performance of the Company.
These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ materially from
those expressed in the forward-looking information. Actual results and future events could differ materially from anticipated
in such information. These and all subsequent written and oral forward-looking information are based on estimates and
opinions of management on the dates they are made and expressly qualified in their entirety by this notice. The Company
assumes no obligation to update forward-looking information should circumstances or management’s estimates or opinions
change.
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally through its equity interest in EnviroCopper Limited. Alligator’s Directors have significant experience in the
exploration, development and operations of both uranium and copper projects.
Projects
About Alligator Energy
Forward Looking Statement
8
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 8 of 14
Alligator Group Tenure Holdings at Quarter End:
The following information is provided pursuant to Listing Rule 5.3.3.
ARUP (NT) Uranium
Licence Number Tenement
Name
Ownership Interest Area
(km2
)
State Status
EL24921
Tin Camp
Creek
TCC Project P/L 100 76.79 NT Granted
EL24922
Tin Camp
Creek
TCC Project P/L 100 194.59 NT Granted
EL25002
Tin Camp
Creek
TCC Project P/L 100 11.55 NT Granted
EL24291 Beatrice Alligator Energy Ltd 100 337.21 NT Granted
EL26796 Beatrice Alligator Energy Ltd 100 19.77 NT Granted
EL27252 Nabarlek North
Northern Prospector
P/L
100 6.75 NT Granted
EL27253 Nabarlek North
Northern Prospector
P/L
100 5.61 NT Granted
EL28389 Nabarlek North
Northern Prospector
P/L
100 110.83 NT Granted
EL28390 Nabarlek North
Northern Prospector
P/L
100 33.58 NT Granted
EL29991 Nabarlek North
Northern Prospector
P/L
100 26.87 NT Granted
EL29992 Nabarlek North
Northern Prospector
P/L
100 63.81 NT Granted
EL29993 Nabarlek North
Northern Prospector
P/L
100 57.06 NT Granted
EL31480 Nabarlek North
Northern Prospector
P/L
100 188.44 NT Granted
EL26793, EL26794,
EL26795
Beatrice Alligator Energy Ltd 100 123.88 NT Application
EL27777, EL27778,
EL28176, EL28293,
EL28315, EL28863,
EL28864, EL28865,
EL28950, EL31452,
EL31453, EL31454,
EL32075, EL32389,
EL32390, EL32391
Various
Northern Prospector
P/L
100 907.44 NT Applications
Eyre Peninsula (SA) Uranium
EL5926 Samphire S Uranium Pty Ltd 100 332 SA Granted
EL6350 Samphire S Uranium Pty Ltd 100 38 SA Granted
EL6835 Samphire S Uranium Pty Ltd 100 61 SA Granted
EL6901 Samphire S Uranium Pty Ltd 100 119 SA
Granted
Cooper Basin (SA) Uranium
EL6367 Big Lake
Big Lake Uranium
Pty Ltd
100 818 SA Granted
EL6847 Big Lake
Big Lake Uranium
Pty Ltd
100 841 SA Granted
EL6848 Big Lake
Big Lake Uranium
Pty Ltd
100 877 SA Granted
EL6849 Big Lake
Big Lake Uranium
Pty Ltd
100 978 SA Granted
EL6902 Big Lake
Big Lake Uranium
Pty Ltd
100 939 SA Granted
EL6903 Big Lake
Big Lake Uranium
Pty Ltd
100 994 SA Granted
EL6904 Big Lake
Big Lake Uranium
Pty Ltd
100 975 SA Granted
9
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 9 of 14
Blackbush Mineral Resource Estimate reported above a 250ppm U3O8 cut-off.
JORC Category Mt
Grade
(U3O8 ppm)
U3O8 Metal
(Mlbs)
Indicated 8.2 786 14.2
Inferred 3.9 443 3.8
Total 12.1 676 18.0
The model is reported unconstrained and above a 250 ppm U3O8 lower cut-off grade for all zones in
consideration of potential for recovery by in situ leach processes.
There is no historical depletion by production within the model area.
Estimation of the disequilibrium factored and topcut gamma data (feU3O8c) is by ordinary kriging using
dynamic anisotropy for the mineralised zone.
Density is estimated by nearest neighbour estimation within the Kanaka Beds on the basis of logged geology
as either 1.79 t/m3 for lignitic material or 1.92 t/m3 for other sediments; other paleochannel stratigraphies
had a default of 1.90 t/m3 assigned; saprolite capping the basement granite was assigned a bulk density of
2.16 t/m3 and the primary basement granite was assigned a nominal bulk density of 2.70 t/m3.
The model assumes agglomeration of 12.5mE x 12.5mN x 1mRL parent blocks for definition of well fields for
production.
The model does not account for dilution, ore loss, hydrogeology, or recovery issues. These parameters should
be considered during the mining study as being dependent on the ISL treatment process.
Classification is according to JORC Code Mineral Resource categories.
Totals may vary due to rounded figures.
The mineral resource estimate in this report was reported by the Company in accordance with listing rule 5.8
on 6 May 2025. The Company confirms it is not aware of any new information or data that materially affects
the information included in the previous announcement and that all material assumptions and technical
parameters underpinning the estimates in the previous announcement continue to apply and have not
materially changed.
10
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 10 of 14
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Alligator Energy Limited
ABN Quarter ended (“current quarter”)
140 575 604 30 September 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (incl State Payroll Taxes) (490) (490)
(e) administration and corporate costs (580) (580)
1.3 Dividends received (see note 3) - -
1.4 Interest received 234 234
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives 702 702
1.8 Other (annual insurances) (128) (128)
1.9 Net cash from / (used in) operating
activities
(262) (262)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (incl
FRT construction)
(775) (775)
(d) exploration & evaluation (1,005) (1,005)
(e) investments (EnviroCopper) - -
(f) other non-current assets - -
11
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 11 of 14
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (property and tenement bonds) (2,690) (2,690)
2.6 Net cash from / (used in) investing
activities
(4,470) (4,470)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(88) (88)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (lease payments) (20) (20)
3.10 Net cash from / (used in) financing
activities
(108) (108)
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
30,114 30,114
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(262) (262)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(4,470) (4,470)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
(108) (108)
12
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 12 of 14
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
25,274 25,274
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to
the related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 4,774 22,114
5.2 Call deposits 20,500 8,000
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
25,274 30,114
6. Payments to related parties of the entity and their associates Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
138
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a
description of, and an explanation for, such payments.
NOTE: The payment amounts disclosed in 6.1 above relate to director fees for Non-Executive
Directors together with the salary for the CEO
13
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 13 of 14
7. Financing facilities
Note: the term “facility’ includes all forms of
financing arrangements available to the
entity.
Add notes as necessary for an
understanding of the sources of finance
available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (262)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(4,470)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (4,732)
8.4 Cash and cash equivalents at quarter end (item 4.6) 25,274
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 25,274
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
5.3
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3,
answer item 8.7 as “N/A”. Otherwise, a figure for the estimated quarters of funding available
must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
14
info@alligatorenergy.com.au | www.alligatorenergy.com.au | +61 (0) 7 3839 3904
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | Page 14 of 14
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above
must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: .........29 October 2025..........................................................................
Authorised by: ..................Board of Directors.................................................................
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s
activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes
to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and
provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to
this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX
pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it
has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of
board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a disclosure committee,
you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards and
gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound system
of risk management and internal control which is operating effectively.