Final Operating Plan Submitted - Samphire Trial
Released
Released
Announcement PDF
ASX Announcement
10 March 2025
Final Operating Plan submitted for assessment to
allow Samphire Field Recovery Trial start
Alligator Energy (ASX: AGE, ‘Alligator’ or ‘the Company’) is pleased to confirm that the
Program for Environment Protection and Rehabilitation (PEPR) for conducting the in-situ Field
Recovery Trial (FRT) at the Samphire Uranium Project, near Whyalla, South Australia has been
submitted and is now in the assessment phase.
Highlights:
• The conditions attaching to the Retention Lease (RL) received in January 2025
have been factored into a Program for Environment Protection and
Rehabilitation (PEPR).
• Additional clarification meetings were held with the SA Department for Energy
and Mining (DEM), the Environment Protection Agency (EPA), and the
Department of Environment and Water (DEW) specialists prior to submission.
• These three Government Departments, led by the DEM, will be assessing the
PEPR. This document, once approved, will form the operating plan for the Field
Recovery Trial. While we anticipate the PEPR approval process may take some
months (see Fig 2), it is hoped that the clarification meetings serve to minimise
any extension of time that arise from additional information requests.
• Approval of the PEPR and EPA construction and operating permits represent
the final steps in the regulatory process.
• Alligator has the prefabricated pilot FRT plant and major consumables already
in its Whyalla yard, and our experienced ISR team is ready.
• Alligator has a team of 15 ISR experienced managers, technical and
environmental specialists, on-site drilling, geology and field technicians,
including 4 Whyalla-based employees.
• A preferred Whyalla based contractor, Ahrens Group Pty Ltd, has been selected
for the on-site construction of the pilot plant and associated civils, along with
the pipe works and pumps to connect with the three trial-production well
patterns. The construction contract will be ready for signing once the PEPR and
EPA permits are approved.
• Ahrens is ready to mobilise their team and subcontractors in the Whyalla region
(estimated at up to 25 skilled construction and trades people) for the 2 to 3
months construction and commissioning phase.
• The commencement of the Field Recovery Trial will cement Samphire’s place
as the next potential ISR uranium mine in South Australia.
Alligator’s CEO Greg Hall stated: “Our Samphire team, led by COO Andrea Marsland-Smith,
have worked continuously to deliver this important and detailed document. We are very pleased
to be advancing the Samphire Uranium project through this key task to establish final technical
operating parameters and de-risk the future technical / production process. The output results will
feed directly into a Feasibility Study.
Once we are close to constructing this pilot plant, we will be calling for expressions of interest from
engineering firms with suitable experience to run a Definitive Feasibility Study for a future full-scale
ISR mine and process plant. The aim is to have the core feasibility team in place while the FRT is
in operation during the second half of this year, with studies continuing into 1H 2026.”
Objectives of the Program for Environment Protection and Rehabilitation (PEPR)
The Retention Lease document received in January 2025, contained a number of conditions
(environmental outcomes) covering a range of important areas, including, stakeholder engagement
processes; groundwater management; soil, vegetation and fauna strategies; air quality; radiation
management; traffic, noise and public safety. These conditions, after further consultation with the
Department for Energy and Mining and the co-regulators being the Department for Environment
and Water and the EPA, have been incorporated into the PEPR. This document, once approved,
governs how the trial will be conducted.
Approval of the PEPR is the final step in the DEM regulatory process to commence on-site
construction of the FRT infrastructure, with an EPA site permit process also underway.
Recap of the objectives of the FRT
1. Designed to confirm key parameters of a future production operation and marks an
important step toward development.
2. Parameters to be assessed include in-situ chemistry, hydrogeology, uranium recovery,
reagent usage, and other environmental and economic factors.
3. Data and learnings further de-risk the Project and provide the necessary inputs to a
definitive feasibility study and Mining Lease Application to be commenced during 2H 2025.
The FRT operations will be conducted over a period of three to four months after construction and
commissioning is completed (targeted during Q3 2025 (refer Fig 2 – Indicative Samphire FRT
Schedule) and will involve establishing three well-field patterns (refer Fig 1) and placement and
construction of a pilot processing plant (already fabricated). Post completion of the FRT operations,
and any additional test work identified in the short-term, the pilot plant and wellfields will be
removed, and the area rehabilitated.
2
Fig 1 – Layout of the FRT production wellfields and pilot plant site.
Fig 2 – Indicative Schedule for Samphire Field Recovery Trial - PEPR approval, construction and FRT
operations. Subject to Department of Energy and Mining (and Co-Regulators) approval of the PEPR
as estimated.
This announcement was authorised for release by the CEO and Managing Director.
3
Contacts
For more information, please contact:
Mr Greg Hall
Mr Mike Meintjes
CEO & Managing Director
Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
Forward Looking Statement
This announcement contains projections and forward-looking information that involve various risks and uncertainties
regarding future events. Such forward-looking information can include without limitation statements based on current
expectations involving a number of risks and uncertainties and are not guarantees of future performance of the
Company. These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ
materially from those expressed in the forward-looking information. Actual results and future events could differ
materially from anticipated in such information. These and all subsequent written and oral forward-looking information
are based on estimates and opinions of management on the dates they are made and expressly qualified in their
entirety by this notice. The Company assumes no obligation to update forward-looking information should
circumstances or management’s estimates or opinions change.
Competent Person’s Statement
Information in this report that supports plans for a field recovery trial is based on current and historic Exploration and
Resource Drilling Results compiled by Dr Andrea Marsland-Smith who is a Member of the AusIMM. Dr Marsland-Smith
is employed on a full-time basis with Alligator Energy as Chief Operating Officer, and has sufficient experience which is
relevant to the style of mineralisation and type of deposit under consideration (including 21 years in ISR uranium mining
operations and technical work) and to the activity she is undertaking to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr
Marsland-Smith consents to the inclusion in this release of the matters based on her information in the form and context
in which it appears.
4
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration, development and
operations of both uranium and nickel projects (both laterites and sulphides).