Big Lake Project - Drilling Update
Released
Released
Announcement PDF
ASX Announcement
8 April 2025
Big Lake Project Drilling Update, South Australia
Alligator Energy Limited ASX: AGE (Alligator or the Company) advises that its follow-up drill
program at the Big Lake Uranium Project (Big Lake) in the Lake Eyre Basin, South Australia has
been curtailed due to the imminent arrival of flood waters from the significant rain event in Western
Queensland.
Highlights
•
In late February 2025 the Company initiated a rotary mud drilling program at the Big Lake
Project targeting both the Namba and Eyre formations. After initial equipment commissioning
issues, two drill holes were completed.
•
In the past two weeks the Company has been monitoring the implications of the recent
significant rain event in Western Queensland for its impact on the channel country flowing
across our exploration licences down to Lake Eyre.
•
Flood alerts have now been issued for both the Cooper and Strzelecki Creek with local
graziers and oil and gas companies commencing flood mitigation procedures.
•
Many of Alligator’s planned drilling areas will be impacted, including our mobile camp site,
and road access to Moomba and surrounds is anticipated to be totally cut off. As of Monday,
the Cooper Creek had risen enough such that water was flowing into the Strzelecki Creek.
•
After considering the potential for a significant period of disruption and the safety of personnel
and equipment, the Company decided to commence demobilisation procedures and has
issued a force majeure notice to its drilling contractor.
•
Drilling and camp areas have now been made safe and all equipment removed. One drill
hole has been fully rehabilitated, and one capped and sealed for future re-access. The drilling
company has de-mobilised, as have Alligator personnel and vehicles.
•
It is unknown how long the area may be inaccessible, but flood levels and duration are
anticipated to be similar to other large flood events, e.g. the 1974 flood.
•
Our initial holes encountered similar oxidised sands to last years drilling, and one hole was
successfully gamma probed with results pending due to the de-mobilisation.
Alligator’s CEO Greg Hall stated: “I thank our Alligator team and the drilling crews for their rapid and
detailed planning, regular communication and quick actions in being able to safely de-mobilise at short
notice. While we did anticipate the flood event, we believed there was adequate time to complete tasks –
however the continued rain events in Western QLD brought forward the timing. Alligator also thanks the
excellent help and advice from SANTOS personnel and contractors who have provided temporary storage
space in yards in Moomba.”
Alligator Energy will keep the market informed regarding flood levels and duration, and any
potential timing for possible return to continue drilling.
This released was authorised by Greg Hall, CEO and Managing Director.
1
Contacts
For more information, please contact:
Mr Greg Hall
Mr Mike Meintjes
CEO & Director
CFO & Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
Forward Looking Statement
This announcement contains projections and forward-looking information that involve various risks and
uncertainties regarding future events. Such forward-looking information can include without limitation
statements based on current expectations involving a number of risks and uncertainties and are not guarantees
of future performance of the Company. These risks and uncertainties could cause actual results and the
Company’s plans and objectives to differ materially from
those expressed in the forward-looking information. Actual results and future events could differ materially from
anticipated in such information. These and all subsequent written and oral forward-looking information are
based on estimates and opinions of management on the dates they are made and expressly qualified in their
entirety by this notice. The Company assumes no obligation to update forward-looking information should
circumstances or management’s estimates or opinions change.
Competent Person’s Statement
Information in this report is based on current and historic Exploration Drilling Results compiled by Dr Andrea
Marsland-Smith who is a Member of the AusIMM. Dr Marsland-Smith is employed on a full-time basis with
Alligator Energy as Chief Operating Officer, and has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration (including 21 years in ISR uranium mining operations
and technical work) and to the activity she is undertaking to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves. Dr Marsland-Smith consents to the inclusion in this release of the matters based on her information
in the form and context in which it appears.
ASX: AGE
ASX: AGE
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | +61 (0) 7 3839 3904
info@alligatorenergy.com.au | www.alligatorenergy.com.au | Page 2 of 3
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related
minerals, principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration,
development and operations of both uranium and nickel projects (both laterites and sulphides).
Projects
ASX: AGE
ASX: AGE
ABN 79 140 575 604 | Suite 2, 128 Bowen St, Spring Hill, QLD 4000 | +61 (0) 7 3839 3904
info@alligatorenergy.com.au | www.alligatorenergy.com.au | Page 3 of 3
Share your feedback
Discover