Re-release - Noosa Mining Conference Presentation - July 25
Released
Released
Announcement PDF
ASX Announcement
30 July 2025
Re-release of Noosa Mining Conference
Presentation
Alligator Energy (ASX: AGE, ‘Alligator’ or ‘the Company’) attaches a further re-release of the
Noosa Mining Conference Presentation (23 July 2025) noting the following:
•
An additional slide 10 has now been included in the presentation setting out the
JORC 2012 Code disclosures required in relation to each Public Report that
refers to an Exploration Target. These disclosures and the cautionary statement
are replicated from the Samphire Exploration Target ASX release of 7 December
2023.
•
Alligator retracts the reference in the original presentation (slide 7) on the
intention to consider an increase in production rate upwards to 1.5Mlbs during
the Definitive Feasibility Study. This higher production rate has not been
disclosed in compliance with ASX Listing Rule 5.16 and the Company did not
have a reasonable basis to state this higher production target in accordance with
ASX Listing Rule 5.16. Investors should not rely on this information to make any
investment decisions in the Company.
This announcement was authorised for release by the CEO.
Contacts
For more information, please contact:
Ms Andrea Marsland-Smith
Mr Mike Meintjes
CEO
Company Secretary
ams@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration, development and
operations of both uranium and nickel projects (both laterites and sulphides).
Projects
2
ASX:AGE
Advancing Samphire Uranium
Project into Trial Production
Andrea Marsland-Smith CEO
23 July 2025
Disclaimer
Forward Looking Statements
This presentation contains projections and forward-looking information that involve various risks and uncertainties regarding future events. Such forward-looking information can
include without limitation statements based on current expectations involving a number of risks and uncertainties and are not guarantees of future performance of the Company.
These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ materially from those expressed in the forward-looking information. Actual
results and future events could differ materially from anticipated in such information. These and all subsequent written and oral forward-looking information are based on estimates
and opinions of management on the dates they are made and expressly qualified in their entirety by this notice. The Company assumes no obligation to update forward-looking
information should circumstances or management’s estimates or opinions change.
Competent Person’s Statement – Uranium and Previously Reported Information
Information in this report is based on current and historic Exploration and Resource Drilling Results compiled by Dr Andrea Marsland-Smith, who is a Member of the AusIMM. Dr
Marsland-Smith is employed by Alligator Energy as Chief Executive Officer (CEO) and has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity she is undertaking (including 21 years working with ISR uranium development and operations) to qualify as a Competent Person as defined in
the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr Marsland-Smith consents to the inclusion in this release of
the matters based on her information in the form and context in which it appears.
Information in this report that relates to the Exploration Target estimate was compiled by Dr Andrea Marsland-Smith, who is a Member of the AusIMM. Dr Marsland-Smith is
employed by Alligator Energy as Chief Executive Officer (CEO) and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration
and to the activity she is undertaking (including 21 years working with ISR uranium development and operations) to qualify as a Competent Person as defined in the 2012 Edition of
the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr Marsland-Smith consents to the inclusion in this release of the matters based
on her information in the form and context in which it appears.
In relation to Exploration Results, Mineral Resource Estimates and Exploration Target in the ASX announcements referenced on slides 7, 9 & 13, the Company confirms that it is not
aware of any new information or data that materially affects the information included in the original market announcement and that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. In relation to production target referred to on slide 7 & 8, the
Company confirms that all material assumptions underpinning the production target, and the forecast financial information derived from the production target, in the initial
announcement continue to apply and have not materially changed.
2
Alligator Corporate Presentation | July 2025 | ASX:AGE
Company Snapshot
Capital Structure (as at 30 June 2025)
Share Price A$
$0.029
Ordinary Shares
4,430.1 M
Listed & Unlisted Options
460.2M
Cash as at 30 June 2025 (A$)
$ 30.1 M
June Share Placement (post issue costs)
$ 16.2 M
Market Cap A$
$128.5 M
Top 50 Shareholders
30 June 2025
Brokers &
Banks
22.4%
Retail
35.9%
Directors
&
Executives
4.1%
Institutions
37.6%
3
Alligator Corporate Presentation | July 2025 | ASX:AGE
Alligator Energy Limited – Samphire Uranium Project, South Australia
4
Alligator Corporate Presentation | July 2025 | ASX:AGE
•
Safe, tier one uranium mining jurisdiction
•
Proven approvals process – 5 mines approved
•
Staged long life project - significant ISR resource with
known expansion potential
•
Coming to market late this decade
•
On-ground in August this year with In-Situ field recovery
trial
•
Experienced In-Situ uranium mining team
•
New discovery for potential ISR pipeline
Board & Management – uranium development, operational and marketing exp
Paul Dickson | Non-Executive Chairman
Callum McIntyre | Alternate Director
Finance and corporate advisory professional and private equity manager with
more than 30 years’ experience. Specialising in junior and mid-tier ASX listed
resources companies, AGE Board member since inception and Chairman for 3
years.
Extensive experience in the finance and technology industries in Australia and
overseas. Director Business and Investment at a private investment company,
and Business Operations Manager at a private Company focused on exploration
and production of gas in the Perth Basin.
Gregory Hall | Executive Director
Mike Meintjes | CFO & Company Secretary
Mining engineer, marketing professional and CEO with 35+ years’
experience – uranium, nickel, bauxite, alumina, iron ore.
Uranium projects; Olympic Dam, ERA Ranger & Jabiluka, Uranium
marketing for Rio Tinto, CEO of Toro Energy and Alligator Energy Ltd
Chartered Accountant / CFO / Company Secretary. Over 30 years
professional services with a Big Four accounting firm and independent
consulting. Extensive exposure to mining, oil & gas sectors in WA, QLD and
South Africa. CFO and Co Sec for Alligator for 12 years
Peter McIntyre | Non-Executive Director
Dr Andrea Marsland-Smith | CEO
Civil engineer and experienced CEO – General Manager roles with WMC
Ltd, including development of major mining projects.
Founding CEO of Extract Resources - discovery and feasibility of Husab
Uranium mine in Namibia.
Early exploration geologist roles in uranium exploration.
Previously a member of the Executive Management Team at Heathgate
Resources with roles over 17 years covering technical and field positions in
Geology, Head of Geology, Head of Regulatory & Compliance, Head of
Operations and Head of Government Relations and Indigenous Affairs.
Fiona Nicholls | Non-Executive Director
30 years across a range of business functions including strategy, planning,
ESG and operations, multi-country project development, approvals and due
diligence processes
Previously Rio Tinto on the Board of Rössing Uranium and ERA uranium.
5
Alligator Corporate Presentation | July 2025 | ASX:AGE
Management and operating team with extensive uranium mine
operations experience, particularly with In-Situ Recovery (ISR),
including stakeholder engagement, approvals, operations, uranium
marketing and contracting, environmental and sustainable production.
Samphire Uranium project: South Australia – Experience in Uranium
20kms from
Whyalla, SA
Iron and steel making centre,
Excellent regional
infrastructure, skilled labourforce, local engineering and
services
6
Alligator Corporate Presentation | July 2025 | ASX:AGE
Samphire Uranium Project: A highly competitive In-Situ Recovery Project
Blackbush Mineral Resource (May 2025)
18 Mlbs
80m (260ft)
Depth of ISR
Plan view of Blackbush channel - Collar locations (pre 2024 blue dots, 2024 in black dots) and current
Indicated (red shell), Inferred (green shell) and Unclassified (pale green shell) MRE .
•
18 Mlbs to support startup mining operation with staged expansion (14.2Mlbs Indicated, 3.8Mlbs
Inferred)
•
Scoping study (Dec 2023) was conducted at US$75/lb which is below today’s LT U price
-
12yr mine life at 1.2 Mlbs production rate per annum
•
Size and integrity ready for detailed well field and future mine design
•
Definitive Feasibility Study (DFS) will consider an increase in production rate upwards from the
current 1.2 Mlbs per annum used in the December 2023 Scoping Study
Refer AGE ASX Release 6 May 2025 - Increased Mineral Resource Estimate and Upgrade of Indicated Resource for the Blackbush Deposit, Samphire U Project.
https://wcsecure.weblink.com.au/pdf/AGE/02943740.pdf and ASX release 14 December 2023 “Scoping Study Update”
7
Alligator Corporate Presentation | July 2025 | ASX:AGE
Samphire Uranium Project – Dec 2023 Scoping Study† : 1.2 Mlbs pa Project
Study metrics* at US$75 / lb long term uranium price
A$131m
2.45 years
42%
A$257m
US$33.31/lb
US$16.06/lb
CAPEX
Payback
IRR*
NPV8*
AISC
Cash Costs
(post-tax, real,
ungeared)
(post-tax, real,
ungeared)
(A$47.58/lb)
(A$22.94 /lb)
(including contingency)
Study metrics* based on analyst's current long-term price projections of US$90 / lb
A$131m
1.93 years
55%
A$371m
US$34.06/lb
US$16.06/lb
CAPEX
Payback
IRR*
NPV8*
AISC
Cash Costs
(post-tax, real,
ungeared)
(post-tax, real,
ungeared)
(A$48.96/lb)
(A$22.94/lb)
(including contingency)
† Ref ASX release 14 December 2023 “Scoping Study Update”: Alligator confirms that all material assumptions underpinning the ‘production target’ or the forecast financial information derived from the ‘production target’ continue to
apply and have not materially changed other than the outlook for the long-term uranium price as set out above; *Calculated using 0.70 US/A$ exchange rate inclusion of significant contingencies and inflation of 35%.
8
Alligator Corporate Presentation | July 2025 | ASX:AGE
Further Extensions outside the Exploration Target Envelope
•
18 Mlbs Resource at Blackbush
•
Second satellite deposit at Plumbush established –
requires closer spaced drilling to become a potential
resource
•
Blackbush
Exploration Target established in late 2023
-
Outstanding continuity of the Samphire palaeochannel system –
~over 90kms of channels.
-
Historical drillholes confirm that extensions contain the same
thick sequences of Kanaka Bed sands which host the Blackbush
Mineral Resource.
-
72% of the prospective areas of the entire Samphire
palaeochannel system remain completely untested by drilling.
-
Significant potential for new discoveries and resource growth in
the Project area.
Refer AGE ASX Release 7 December 2023 - Significant Exploration Target Range established, Samphire Uranium Project, South Australia.
https://wcsecure.weblink.com.au/pdf/AGE/02751150.pdf
9
Alligator Corporate Presentation | July 2025 | ASX:AGE
Plumbush
Exploration Target at Samphire
Exploration Target includes extensions to mineralisation at Blackbush, the Plumbush Prospect as well as
other areas of known mineralisation and potential extensions.
Samphire
Uranium Project
Area
Million Tonnes
(Mt)
eU3O8 (ppm)
Million Pounds
(Mlbs) eU3O8
Total
16 - 37
390 - 903
14 - 75
(Exclusive of the Blackbush Mineral Resource – ASX Announcement 7 Dec 23).
The potential quantity and grade of the Exploration Target is conceptual in nature. There has been insufficient exploration to
estimate a Mineral Resource and it is uncertain if further exploration will result in the estimation of a Mineral Resource. The
Exploration Target has been prepared in accordance with the 2012 Edition of the Australasian Code for Reporting of Exploration
Results, Mineral Resouces and Ore Reserves (‘the JORC Code’)
Refer AGE ASX Release 7 December 2023 - Significant Exploration Target Range established, Samphire Uranium Project, South Australia. https://wcsecure.weblink.com.au/pdf/AGE/02751150.pdf
10 Alligator Corporate Presentation | July 2025 | ASX:AGE
Samphire Uranium Project – Field Recovery Trial (FRT)
• Field Recovery Trial (FRT)
- Final step in de-risking the Project
- Provides the necessary inputs for DFS
- Marks an important step toward full Mining
Lease Application to commence during 2H
2025.
• Plant fully fabricated at AGE’s Whyalla yard ready for
on-site construction.
• Construction targeted for August/September 2025
pending final stage of regulatory approval.
• FRT operation ~ 3+ months (Oct to Dec 2025) and
consists of three producing well patterns and a
containerised pilot plant.
• Alligator ISR team established.
• Parameters to be assessed include in-situ chemistry,
hydrogeology, uranium recovery, reagent usage, and
other environmental and economic factors.
Wellhouse (Pipe room) Module
11 Alligator Corporate Presentation | July 2025 | ASX:AGE
Field Recovery Trial – Plant Layout & Control
Ion Exchange Module
Wellhouse (pipe room) Module
• Whyalla based contractor selected for the on-site construction
• Plant control system set up and tested.
• Post-FRT and subject to any further testing, well infrastructure and
plant to be removed, and area rehabilitated.
• Pilot plant available for future satellite field testing (Plumbush).
• Samples of extracted uranium oxide solution be precipitated offsite
into U3O8 concentrate for Converter quality samples.
Control System
12 Alligator Corporate Presentation | July 2025 | ASX:AGE
Reverse Osmosis Plant
Plans and Targets – 2025 Year and into 2026
13 Alligator Corporate Presentation | July 2025 | ASX:AGE
Big Lake Uranium Project, SA – New Discovery
• Geologically analogous to world-class ISR fields in hydrocarbon
basins - Kazakhstan, Wyoming, Texas.
• Same host sands as Beverley-Four Mile & Honeymoon.
• Province never-before been drilled exploring for uranium.
• Inaugural drilling program (August 2024) intersected significant
thicknesses of anomalous uranium mineralisation.
-
AC24-021
AC24-022
AC24-023
AC24-025
20m (65ft) @ 110 ppm U from 347ft (106m)
35m (114ft) @ 117 ppm U from 305ft (93m)
5m (16ft) @ 47 ppm U from 341ft (104m)
10m (32ft) @ 138 ppm U from 354ft (108m)
• 2025 - Second drilling program commenced but delayed due to
QLD floodwaters.
• Potential to become a new uranium province in South Australia.
• Alligator’s large exploration licence holding secures first mover
advantage.
Alligator Corporate Presentation | July 2025 | ASX:AGE
Refer ASX Announcements: 23 October 2024 – BLU Uranium Discovery, and 27 Feb 2025 – Follow Up drilling at BLU
ASX:AGE
Andrea Marsland-Smith
CEO
+61 (0) 7 3839 3904
ams@alligatorenergy.com.au
www.alligatorenergy.com.au