Alligator Energy (ASX: AGE, ‘Alligator’ or ‘the Company’) is pleased to provide an update on
the status of obtaining the final approvals for conducting the in-situ Field Recovery Trial (FRT) at
the Samphire Uranium Project, near Whyalla, South Australia.
Highlights:
• Since lodging the operating plan for the FRT (Program for Environment
Protection and Rehabilitation (PEPR)) in early March 2025, the Company has
held several clarification meetings with specialists at the co-regulators, namely
SA Department for Energy and Mining (DEM), the Environment Protection
Agency (EPA), and the Department of Environment and Water (DEW).
• These meetings culminated in the receipt of a Request for Information (RFI)
which principally covers questions on hydrogeology, groundwater monitoring
and rehabilitation.
• A formal response to the RFI has now been lodged with the co-regulators with
the Company confident that all matters of clarification can be adequately
addressed in the proposed operating procedures.
• In addition, as also required, Alligator has achieved a key milestone in receiving
its Works Approval Licence from the EPA for construction of the FRT.
• Our construction contractor Ahrens recently visited the FRT site with local subcontractors with the objective of refining the contract sum and advancing
induction and construction start up procedures. Contract negotiations for this
work are close to finalisation.
Alligator’s CEO Greg Hall stated: “Alligator Energy continues to work with our assessors and
regulators to ensure they have all the information needed to advance their assessment of our PEPR
for the operation of the Field Recovery Trial. We look forward to receiving this outcome to initiate
employment of our contractors and our own extra personnel in the Whyalla region.”
Recap of the objectives of the Field Recovery Trial
1. Designed to confirm key parameters of a future production operation and marks an
important step toward development.
2. Parameters to be assessed include in-situ chemistry, hydrogeology, uranium recovery,
reagent usage, and other environmental and economic factors.
3. Data and learnings further de-risk the Project and provide the necessary inputs to a
definitive feasibility study and Mining Lease Application to be commenced during 2H 2025.
The FRT operations will be conducted over a period of three to four months (targeted approximately
from late Q3 2025 dependent on timing of receiving an approved PEPR from the Department for
Energy and Mining) and will involve establishing three well-field patterns and placement and
construction of the pilot processing plant (already fabricated) and associated equipment. Post
completion of the FRT operations, and any additional testwork identified, the pilot plant and
wellfields will be removed and the area rehabilitated.
Fig 1 – Layout of the FRT production wellfields and pilot plant site.
Fig 2 – Ion exchange module; Wellhouse (pipe room) module; Reverse Osmosis plant – all currently
situated in Alligators Whyalla yard
This announcement was authorised for release by the CEO and Managing Director.
2
Contacts
For more information, please contact:
Mr Greg Hall
Mr Mike Meintjes
CEO & Managing Director
Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
Forward Looking Statement
This announcement contains projections and forward-looking information that involve various risks and uncertainties
regarding future events. Such forward-looking information can include without limitation statements based on current
expectations involving a number of risks and uncertainties and are not guarantees of future performance of the
Company. These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ
materially from those expressed in the forward-looking information. Actual results and future events could differ
materially from anticipated in such information. These and all subsequent written and oral forward-looking information
are based on estimates and opinions of management on the dates they are made and expressly qualified in their
entirety by this notice. The Company assumes no obligation to update forward-looking information should
circumstances or management’s estimates or opinions change.
Competent Person’s Statement
Information in this report that supports plans for a field recovery trial is based on current and historic Exploration and
Resource Drilling Results compiled by Dr Andrea Marsland-Smith who is a Member of the AusIMM. Dr Marsland-Smith
is employed on a full-time basis with Alligator Energy as Chief Operating Officer, and has sufficient experience which is
relevant to the style of mineralisation and type of deposit under consideration (including 21 years in ISR uranium mining
operations and technical work) and to the activity she is undertaking to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr
Marsland-Smith consents to the inclusion in this release of the matters based on her information in the form and context
in which it appears.
3
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration, development and
operations of both uranium and nickel projects (both laterites and sulphides).
Projects
4
Share your feedback
Discover