Work Advances at Samphire Uranium Project
Alligator Energy (ASX: AGE, ‘Alligator’ or ‘the Company’) is pleased to provide the following
update covering progress in preparing for the In-Situ Recovery (ISR) Field Recovery Trial (FRT),
the ongoing 2024 Resource extension drilling at the Blackbush Deposit, and other work programs
at the Samphire Uranium Project, near Whyalla, South Australia.
Highlights:
• Fabrication of the FRT processing plant in Adelaide essentially complete and
modules are undergoing Factory Acceptance Testing prior to being transported
to Whyalla ahead of securing the necessary approvals to conduct the trial.
• The Company has recently provided the Department for Energy and Mining
(DEM) a formal response to matters that arose from the public and Govt
Departmental consultation on the Retention Lease (RL) Proposal for the FRT.
The Company anticipates the review period for this response will take six to
eight weeks.
• A Program for Environmental Protection and Rehabilitation (PEPR) will be
submitted post granting of the RL. Approval of the PEPR is the final step in the
regulatory process to commence on-site construction of the FRT infrastructure.
• On-site FRT construction and commissioning plans are under development for
initiation once both the RL and supporting PEPR are approved.
• Drilling on a rotation basis to the west, north-east and south of the current
Blackbush Mineral Resource envelope continues to identify potential
extensions to the uranium roll-front system.
• Ground gravity survey has commenced, designed to delineate the
palaeochannel system south of the known Samphire Uranium deposits
(Blackbush and Plumbush).
Alligator’s CEO Greg Hall stated: “The completion and acceptance testing of the FRT pilot
process containerised IX and wellhouse modules is an important step, and along with the Reverse
Osmosis plant testing (also completed) ensures the Company will be ready for FRT construction
upon granting of the Retention Lease and approval of the PEPR operating plan. Alligator has
communicated widely to stakeholders the detail of its field recovery trial plans, the minimal and very
localised impact this will have, and the important uranium recovery, environmental, rehabilitation
and economic data it will provide.
The resource extension drilling at Blackbush is indicating potential extensions to the current
mineralised envelope, and the first-round drilling data, results and interpretation will be released to
shareholders and the market in the coming months.
An extension of the ground gravity survey onto EL 6350 to the south of the Plumbush deposit –
Alligator’s first work on this EL, is targeting anticipated palaeochannel extensions to the south of
the current channels. There are existing historical intersections of uranium above cut-off grade
within this tenement.”
Field Recovery Trial Update
In August 2023, AGE submitted its full Retention Lease Proposal to DEM to conduct a pilot ISR
field trial. A public review and consultation period for this proposal concluded late September 2023
with formal feedback received from DEM on 20 December 2023 regarding the public and various
SA Government Department’s submissions. Alligator is pleased to advise that Company’s formal
responses to the matters raised from the consultation have been submitted to DEM. We have been
advised the review period for this response will take six to eight weeks pending no further
clarifications being required. A Program for Environmental Protection and Rehabilitation (PEPR) is
currently being drafted and will be submitted post granting of the RL. Approval of the PEPR is the
final step in the regulatory process to commence on-site construction of the FRT infrastructure.
Fabrication of the containerised FRT plant by Adelaide Control Engineering is essentially complete
with the ion exchange and wellhouse modules commencing Factory Acceptance Testing on 19
March 2024 prior to transport to Whyalla. The scope for on-site assembly is being prepared for
requests to quote from Whyalla-based construction contractors/businesses.
Figure 1: IX columns completed installation inside container. Pump skids in the foreground connected in readiness for
Factory Acceptance Testing.
Resource Extension Drilling Update
Since 29 January 2024, the Company’s rotary mud drilling contractor has been drilling on a rotation
basis (2 week on 1 week off). To date 30 holes have been drilled (2,437 metres) with the first-round
program scheduled to continue through to the mid-April when a 4 to 6 week break will be taken to
facilitate pastoral activities (lambing).
The drilling to date has been focussed on drill testing three areas, including:
• area immediately adjacent to the western limits of the Blackbush West mineralised
envelope;
• an area ~300-400m east of Blackbush East, and;
• southern palaeochannel extensions to the mineralised envelope.
Figure 2: Current Inferred resource area outline (blue) and Indicated Resource area outline (red) of Blackbush minerals
resource estimate (Refer to AGE ASX release dated 7 December 2023: “Successful Upgrade of Indicated Minerals
Resource – Samphire”).
Currently, drilling to the west of Blackbush West appears to be extending the mineralisation by
approximately 100 to 200 m from the boundary of the known Mineral Resource envelope. Similarly
drilling to the east of Blackbush East has identified the presence of mineralised roll-fronts in the
closest of the target areas (indicated by purple circles on the above map).
Drilling will continue in these areas along with the southern palaeochannel extension to approx.
mid-April after which a 1-month break will commence to accommodate pastoral activities. During
this time Alligator will update the market on the first-round results and data. Drilling will resume
mid-late May and will continue to the end of the year when a full JORC compliant mineral resource
update will be undertaken.
Commencement of additional Acquisition of Ground Gravity
The AGE team has assessed the historical regional geophysics to select the optimal geophysical
method for mapping the Samphire palaeochannel system (host to the uranium mineralisation at the
Blackbush deposit and Plumbush prospect). The Samphire palaeochannel is incised into the
Hiltaba Suite Samphire Granite which provides a lithological density contrast at the contact which
ground gravity can successfully detect. The historical gravity data collected at 100m x 200m grid
spacing shows an excellent correlation between gravity-mapped paleochannels and drilling (Figure
2).
Daishsat Geodetic Surveyors are now on location acquiring ground gravity data south of the
Plumbush prospect on Exploration License (EL) 6350 where historical drilling1 shows the presence
of paleochannel-hosted uranium mineralisation. In addition, Daishsat will acquire gravity data north
of the Blackbush system on EL5926 to delineate further palaeochannels in areas where channels
have not yet been delineated but are believed to exist (Figure 3).
With 64 kms of known palaeochannel strike length, only 10% of the prospective system (Blackbush
Deposit and portion of Plumbush Prospect) have been well explored, with a further 32% only partly
drill tested on wide drill spacings. The data from the current gravity survey will complete Alligators
understanding of extensions to the system adding further potential target areas to its pipeline of
future exploration drilling programs.
1 Refer UraniumSA ASX Release – 8 April 2011 “Maiden Resource Estimate”,
https://www.asx.com.au/asxpdf/20110408/pdf/41xy4brvxj3d3c.pdf
Figure 3: AGE’s Samphire project tenement holding showing location of historical and recent (AGE) drillholes, historical
ground gravity, the extent of the Samphire palaeochannel system, historical uranium intersections near the Plumbush
prospect1 and location of area acquisition of new ground gravity data.
This announcement was authorised for release by the CEO and Managing Director.
Contacts
For more information, please contact:
Mr Greg Hall
Mr Mike Meintjes
CEO & Managing Director
Company Secretary
gh@alligatorenergy.com.au
mm@alligatorenergy.com.au
For media enquiries, please contact:
Alex Cowie
Media & Investor Relations
alexc@nwrcommunications.com.au
Forward Looking Statement
This announcement contains projections and forward-looking information that involve various risks and uncertainties
regarding future events. Such forward-looking information can include without limitation statements based on current
expectations involving a number of risks and uncertainties and are not guarantees of future performance of the
Company. These risks and uncertainties could cause actual results and the Company’s plans and objectives to differ
materially from those expressed in the forward-looking information. Actual results and future events could differ
materially from anticipated in such information. These and all subsequent written and oral forward-looking information
are based on estimates and opinions of management on the dates they are made and expressly qualified in their
entirety by this notice. The Company assumes no obligation to update forward-looking information should
circumstances or management’s estimates or opinions change.
Competent Person’s Statement
Information in this report is based on current and historic Exploration and Resource Drilling Results compiled by Dr
Andrea Marsland-Smith who is a Member of the AusIMM. Dr Marsland-Smith is employed on a full-time basis with
Alligator Energy as Chief Operating Officer, and has sufficient experience which is relevant to the style of mineralisation
and type of deposit under consideration (including 21 years in ISR uranium mining operations and technical work) and
to the activity she is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Dr Marsland-Smith consents to the
inclusion in this release of the matters based on her information in the form and context in which it appears.
About Alligator Energy
Alligator Energy Ltd is an Australian, ASX-listed, exploration company focused on uranium and energy related minerals,
principally cobalt-nickel. Alligator’s Directors have significant experience in the exploration, development and
operations of both uranium and nickel projects (both laterites and sulphides).